Join Us Sunday
Services being held at Baker Chapel
Worship 9:00 am
Fellowship 10:15 am
Life Groups 10:30 am


Quick Links



 


 

 

 


Daily Progress Report


Wednesday, August 29, 2007

   Tonight nine of us that are going on the Texas trip next week met at the church for a conference call. Sept. 6-9, ten Baker Chapel members and four other members of the Boonville community will travel to Groesbeck Texas. They along with many other volunteers from around the country will join the New York Says Thank You Foundation build their 2007 project. We will build a new house for James and Eva Vincent and their family. Their house was destroyed by a tornado last December. For more information about the family and the foundation, visit their website newyorksaysthankyou.org

Participating in the conference call were the following:
Baker Chapel
Jeff - New York Says Thank You Foundation Co-founder and organizer of the build projects.
Starvos - New York Says Thank You Foundation Co-founder and General contractor.
Bob - Lead Builder on this project.
Brian - Pre-construction Services Manager for a construction company in Dallas Texas.
Charlie - He was the Construction Supervisor in charge of the Twin Tower clean-up in New York.

Those of us at Baker Chapel spent one hour finalizing our travel plans and preparing questions for the conference call. The purpose of the conference call was to get everybody updated on the project. We were able to establish a projected time-line for the different areas of construction. The house consists of 2700 square feet with a covered porch and an additional garage. They will pour the concrete tomorrow morning. We intend to arrive in Texas on Sept. 6 in the early afternoon. We will evaluate the sight and help prepare the lay out. The work days will be Sept. 7-8. We hope to have the house completely framed, siding installed, decked and a possibility of roofing as well in these two days. If it is God's will, his plan and his time-line, we beleive it is possible. We at Baker Chapel are very excited about having this opportunity, to give something back by "paying forward".

Philip
 

Monday, August 27, 2007
Tuesday, August 28, 2007

   Volunteers worked today grading, seeding grass and covering with straw. They also started watering the seeded areas today. It has been very hot and dry here. I think the temperature has been above 91 degrees for the last 24 days. They decided that we needed to get the grass starting to grow. It needs to get some growth on it before this fall.

Philip
 

Sunday, August 26, 2007

DEDICATION SUNDAY!

   Open House was held from 1:00 to 5:30 p.m. With the dedication service beginning at 5:30 p.m. Six different singing groups entertained in the sanctuary all afternoon. They included; New Harmony Voices, Mt. Gilead Singers, First Baptist Church, Lighthouse Praise Team, The Holders, and the Baker Chapel Praise Team. The opening song for the Dedication Service was "I'll Fly Away". This was the first song that was in the bulletin November 6, 2005, the day the tornado hit. We recognized four former pastors who were in attendance today. Their was a time of reflection. A few people spoke about a specific experience with Baker Chapel. Most of them were about the tornado or since that time. District Superintendent Rev. Glenn Howell shared words and performed the Consecration of the Building. The closing song led by the Gentry Sisters and the Baker Chapel Praise Team was "We are Standing on Holy Ground". The scripture for the service was Psalm Chapter 84: 1-4, 10-12 and Matthew Chapter 7: 24-27. Over 600 people signed the registration book through out the day. And I am quite certain that many people missed the book. We also severed BBQ pork, hamburgers, hot dogs, drinks, cake and many varieties of homemade cookies. It was a blessed day to thank the many volunteers, and to give God all the Glory, for what he has done.

Philip
 

Saturday, August 25, 2007

   Volunteer members finished food preparation today. Others worked outside grading the parking lot, mowing, trimming, and picking up materials to allow more parking. They prepared the programs, and did last minute cleaning, and installed pictures on some walls.

Philip
 

Friday, August 24, 2007

   Volunteers worked at the church today preparing food. They are making potato salad, slaw, veggie trays, bake beans, and a host of other things for the Dedication this Sunday. Others worked on cleaning.

Philip
 

Thursday, August 23, 2007

   I arrived on site this morning at 5:05 a.m. Neil and his concrete crew and Kevin were already working with lights. The concrete pumper truck was setting up, and the laser screed was being prepared. The first load of concrete began unloading at 5:35 a.m. The last full concrete truck was unloaded at 7:58 a.m. The remaining concrete needed was measured and called in for delivery. By approx 8:45 a.m. with a little help from a few volunteers the last of the concrete was poured for a total of 72 yards. By 2:00 p.m. the concrete had been troweled, grooves cut and sealer applied. The concrete had coloring installed. I don't know the "official" color. But I will describe it as a "light colored chocolate". They finished none too soon, as temperatures reached 100 degrees this afternoon. Other volunteers removed forms from yesterdays concrete and seeded grass on the former building site.

Philip
 

Wednesday, August 22, 2007

   Neil and his concrete crew returned today. His crew along with other volunteers, set the J-bolts in concrete to attach the side-wall plates. They also constructed and poured the concrete pads that the pillars will be installed on, for the drive-thru canopy. They installed the rock base, and prepared the area for the concrete floor. Tonight, several volunteers worked on cleaning the inside of the church. We also installed several signs, posters, and did things in preparation for the open house on Sunday August 26.

Philip
 

Tuesday, August 21, 2007

   Volunteers finished placing the back fill (with rock) around the foundation. This evening, Spike put some more top soil onto the old building site, in preparation for seeding.

Philip
 

Monday, August 20, 2007

   Volunteers returned today. They installed the perimeter drain tile, around the foundation of the Life Center/gym. They covered the tile with rock. They also installed the insulation on the inside next to the block, and back-filled with rock. They removed the bottom four feet of siding on the east side of the church. Eventually all of the siding on the east side will be removed. It will be reinstalled on the sides of the Life Center. They removed the bottom four feet only, so it did not get any concrete on it, when the floor is poured.

Philip
 

Thursday, August 16, 2007

   Six block layers arrived today. They installed two rows of 12 inch block, and one row of 8 inch blocks. They have completed all the block work for now. The remaining split-face block can not be installed until the walls are constructed. Volunteers installed more erosion control blankets in the drainage area. They also seeded more grass seed, and strawed the area.

Philip
 

Wednesday, August 15, 2007

   The concrete blocks, sand and cement was delivered today for the multi-purpose building. Greg finished removing the rest of the old asphalt this evening. Spike, Kevin, and Derek worked on hauling and leveling dirt on the old building site. They also installed some rip-rap around the large culvert under the entrance. The Praise team practiced tonight for their part in the Dedication Celebration. The decorating committee met tonight making plans. Today was also the 18th day in a row for temperatures over 90 degrees. The actual temperature reached 104 degrees today. This was the hottest day since back in 1966.

Philip
 

Tuesday, August 14, 2007

   Volunteers poured concrete pads in front of the doors on the south and west sides of the church today. They also sowed more grass seed, and covered it with straw. We worked on removing some of the old asphalt this evening.

Philip
 

Monday, August 13, 2007

   Neal and his concrete crew arrived today. They along with other volunteers, had a very big, progressive day. They dug the footings, installed the re-bar and poured the concrete. These are the footings for the multi-purpose building. They also did the same thing for the four columns, that will support the overhead drive-thru. Once this is completed, you will be able to drive a car under the canopy to load and unload in inclement weather. It was very hot today, but we stuck with it, until the task was completed. I also delivered several bales of straw, that they used to cover the seeded areas.

Philip
 

Wednesday, June 20, 2007

   I went to the church early today before going to work. I moved
some dirt from the top soil pile to where we took up the old parking
lot. I did this for two reasons. The dirt pan we are using belongs
to the Warrick County Soil and Water District. They have been letting
us use the dirt pan free of charge. They rent it out for people to
use. Someone wanted to rent it, and they were coming to pick it up
today. The other reason is; I needed little one on one "God Time". I
will be giving the message next Sunday June 24, I needed to clear my
thoughts.

Philip
 

Saturday, June 16, 2007

   I finished hauling away the rest of the busted asphalt today. I
was also able to separate two loads of rock that was under the old
parking lot. I dumped it in the corner of the new parking lot. We
can use this for base at a later day. I also loaded three wagon loads
of straw behind the baler for us to use for landscaping.

Philip
 

Friday, June 15, 2007

   I started hauling away the busted up asphalt from the parking lot
this evening.

Philip
 

Wednesday, June 6, 2007

   Greg finished busting up the remainder of the old parking lot on
the west side. He also graded some more dirt around the drainage
ditch.

Philip
 

Monday, June 4, 2007

   Greg worked on leveling more dirt around the drainage ditch. He
also put some top soil around this area for seeding.

Philip
 

Saturday, June 9, 2007

   Greg and Derek worked a couple hours this morning moving top
soil, working on the drainage ditch, and they started tearing up the
asphalt in the old parking lot on the west. We have not had any
measurable rain for about three weeks, it is very dry.

Philip
 

Thursday, June 7, 2007

   They delivered the pipes for in the ground for the gutter
downspouts today. Sunburst Stained Glass company of Newburgh
installed the stained glass above the front door today. They donated
the glass and labor. It measures 72" X 72", and is just beautiful.
Greg moved more dirt this evening.

Philip
 

Wednesday, June 6, 2007

   The Operators Union delivered a small dozer today, for us to
use. Greg started this evening using the dozer to grade and level the
drainage ditch. Volunteers worked some this week moving in and
cleaning more items.

Philip
 

Sunday, May 27, 2007

AWESOME!!!!!

   Today was the first official service in God's new church. The
praise team started practice at 8:00 this morning, and people began
arriving for church at 8:05. Church starts at 9:00. When we held our
service at other places, most of the time people would start arriving
only 20 minutes before service. I sat in the hallway before the
service, and just listened to the people has they came in the
building. Some of the comments I over heard were; "We should just
dance", "Just Amazing", "Wonderful", "It's so beautiful". Their were
a lot of new faces, and some we haven't seen for awhile. Their were
158 who celebrated in God's house today at Baker Chapel. We began the
service with the congregation singing; 'I'll Fly Away'. This was
supposed to be the first song on the morning of the tornado. It was a
very tearful and moving experience for many, myself included. Most of
the message included comments from several members, as well as some
guests. Most talked about their experience during the rebuilding, or
shared what Baker Chapel means to them. Prior to singing our closing
song, 'Standing on the Promises'. The Gentry trio sang God Bess
America. The Holy Spirit was truly among us today.

Philip

 
Saturday, May 26, 2007

   First of all, I want to apologize for not giving daily updates
this week. I have been working 16&17 hours a day trying to get the
crops out and hay baled. I even missed praise team practice this
week. I was going back over some of the updates the other night and
realized that I had left out two very important things. We received a
$2500 donation from the children in a Jewish Day School in New York
City last month. This was money that they themselves raised. They
want us to use this money to buy supplies for our Sunday School. I
also failed to mention that starting last Easter morning, people began
writing scripture on the concrete floors. Some people signed their
name with the scripture, some did not. I wish that I had took the
time to write down each of the different scriptures that people had
written. It was really neat, to see different ones show up almost
everyday. I made a couple phone calls last night to find out what
took place this week. Now for this week's progress report.
Our dishwasher and ice machine was delivered on Wednesday. Thursday
night about seven people met in the evening for training on how to
operate the sound system. On Friday the sound system was completed.
A new couch and two new chairs were also delivered on Friday. They
will be in the hallway. We will be having our first service in the
completed church tomorrow May 27, 2007. It is not really a secret,
but we wanted to keep a low profile on our first service. It had been
announced at church the last two Sunday's. Members who were not in
church received an e-mail or letter. The media has been very good to
us, but we wanted our first service too be just us. It is not really
a secret anymore. Their was an article on the front page of the
Evansville Courier today, telling about our first service tomorrow. I
am really excited, and I expect this "special" first service, to be
the first of many.

Philip
 

Friday, May 18, 2007

   Some more new tables arrived today. Our new piano for the
sanctuary was also delivered. We are leasing with the option to
purchase. We are going to try this piano and if we do not like it,
they will bring us another style. Volunteers did more cleaning.

Philip
 

Thursday, May 17, 2007

   The county building inspector came today. He inspected the
entire facility. He discovered a few small things that he would like
changed. However, he did approve that it was ready for occupancy.
Volunteers cleaned several folding chairs, and started wiping the
dusty walls.

Philip
 

Wednesday, May 16, 2007

   The last two doors were delivered today. Volunteers installed
these doors, and all of the remaining hardware, on all the doors. The
carpet installers returned today and finished all the carpet trim, for
the baseboard. Volunteers also cleaned more dishes.

Philip
 

Monday, May 14, 2007
Tuesday, May 15, 2007

   The company came and installed the wire mesh safety glass in the
inside doors that have windows. The four entrance doors into the
sanctuary, have a window in the shape of a cross. The carpet
installers have installed the 4 inch carpet boarder on the walls in
the sanctuary, and the fellowship hall. They also installed the
mud/tracker carpet in the foyer entrance. I am not sure if that is
exactly what it is called, but it is supposed to keep dirt from being
tracked in the building. Volunteers worked Tues. evening cleaning out
the utility room, and cleaning up. Some of the items were put in the
storage trailer, and some items upstairs in the attic storage. They
worked on several small things, that needed finished.

Philip
 

Saturday, May 12, 2007

   Today, God showed me that his plans, and his schedule were
different than what I had planned. You see I had planned to work
ground most of the night last night, and try to finish planting corn
today. Then travel to Purdue University where my daughter will
graduate tomorrow. Well it rained yesterday. So instead of being in
the fields, I got to help 20 plus other volunteers move pews into the
church. These pews were donated to us last year from First Christian
Church in Newburgh Indiana. We had them stored in a building at the
Spencer County fairgrounds. With four trailers we were able to move
them all in one trip except for two pews. Sid and Marsha spent many
hours cleaning the upholstery and the wood work. I think they look
great. I think their are 22 pews, and they fill the sanctuary. They
should seat a little over 200 people. Other volunteers finished
installing door closure's, finished installing the hardware and braces
on the restroom stalls, paper holders and other small jobs. I still
left for Purdue, I just had the pleasure of helping move the pews
before leaving. They also cleaned, and brought a few more things into
the building. We still need to finish some things, and have the
building inspector return. I can just say, that everyday is a day
closer to completion.

Philip

 
Friday, May 11, 2007

   I forgot to mention that the sound guy came yesterday, and he
brought more of the sound system. He worked on securing the ends on
several of the sound cables. Only one carpet installer worked today.
He finished the steps on the stage in the sanctuary. He also cut all
the strips for the base board. We are using carpet as a base board in
every area where their is carpet. He will take these strips back to
the carpet shop, to have the top edge sewed. Volunteers cleaned more
dishes, and placed them in the kitchen cabinets. The lock smith came
and installed all of the lock cylinders on the doors with locks. Greg
and Kevin worked on installing panic bars on the required doors this
evening. It rained this afternoon.

Philip
 

Thursday, May 10, 2007

   Only two carpet installers worked today. They installed the
carpet on the stage, the sound room, and the reading platform in one
of the classrooms. Volunteers installed the remaining door closure's
that we have on hand. Two of the closure's are on back order.

Philip
 

Wednesday, May 9, 2007

   The carpet installers finished the carpet on the sanctuary main
floor. Their is a 16 inch boarder around the sanctuary with a
different color carpet. This was very time consuming. Volunteers
installed two more door closure's this evening.

Philip
 

Tuesday, May 8, 2007

   The carpet installers returned today. They started installing
the carpet in the sanctuary. They completed over 1/2 of the floor.
Ten new round tables were delivered today for the fellowship hall.
Volunteers installed two more door closure's tonight.

Philip
 

Monday, May 7, 2007

Volunteers cleaned dishes and some folding chairs today. A few
of the dishes were salvaged from the tornado. Some of the dishes were
donated by another church. Volunteers also installed door handles
today. Kevin and Greg worked tonight installing door closure's and
panic bars. They were still working at 10:00 p.m.

Philip
 

Saturday, May 5, 2007

   At least 11 volunteers worked at different times today. There
might have been more, but that was the count when I left at 1:00. We
finished installing the rest of the doors on hand. We have two more
doors, that we rejected due to shipping damage. We installed several
of the door handles and some closure's. They cleaned the cabinets in
the kitchen, as well as the refrigerator, and floors. They also
cleaned-up in several other areas. They also moved everything out of
the sound room, in preparation for the carpet.

Philip
 

Friday, May 4, 2007

   The carpet installers finished the classroom, library/conference
room, small hallway, utility closet, the room behind the stage wall,
and rolled out some of the carpet for the sanctuary. The rest of the
carpet was delivered today. Volunteers installed the video screen and
some of the automatic door closure's.

Philip
 

Thursday, May 3, 2007

   The carpet installers returned today. They finished the
fellowship hall, youth room, utility closet, and started on one of
the classrooms. I was returning home tonight from a track meet and
stopped by the church. It was after 8 p.m. and Greg and Kevin were
installing some more doors.

Philip
 

Wednesday, May 2, 2007

   They finished installing the carpet in the big hallway, and
started on the fellowship hall today. Tonight I was rained out of
the fields. I helped Greg and Spike install 6 doors. The remaining
hardware for the restroom partitions was delivered today. Everyday is
a day closer to being completed.

Philip
 

Tuesday, May 1, 2007

   Our new freezer was delivered today. The carpet installers
returned today. They installed carpet in one of the classrooms, coat
closet, nursery, infant room, and started on the big hallway.

Philip
 

Monday, April 30, 2007

   Five big rolls of carpet was delivered today. The carpet
installers also started today. They installed the carpet in the
office, and the minister's office. They also installed the carpet pad
on the stage, and the stage steps. Volunteers installed door handles
on the doors that they installed Sat. They put more items into the
storage trailer. We decided instead of just moving things from one
room to another, to stay out of the way of the carpet. We would just
move things one time into the trailer. Some of these items will stay
in the trailer for quite some time.

Philip
 

Sunday, April 29, 2007

   Jerol, Bonnie, and I, worked at the church tonight. Bonnie and
Jerol finished vacuuming the sanctuary and the stage. I repaired and
replaced the three access holes that we cut in the stage floor to
install the speaker wires. I also loaded the scaffolding in my truck,
so it can be returned tomorrow.

Philip
 

Saturday, April28, 2007

   A few volunteers worked today. They installed six of the inside
doors. These doors were in the areas with the tile floor. Others
removed several items from the church and placed them into the storage
trailer. The carpet is scheduled to be delivered on Monday.

Philip
 

Friday, April 27, 2007

   The interior doors were delivered today. We have 30 inside
doors. We rejected two of them because they were damaged. There was
no school today. It was a scheduled 'snow make-up day'. Since school
was never closed due to snow, the kids got the day off. Some of them
helped to unload and carry in the doors. Five of us worked tonight.
We cleaned the saw dust out of all the cabinets, swept and vacuumed
most of the floors, picked up debris. We did not get finished, but
we did get tired. We stopped at 10:00 p.m.

Philip
 

Thursday, April 26, 2007

   The plumbers returned today. They finished installing all of the
sinks except two. Installed all the in-line water heaters. They have
the water turned on and everything checked. They will have to return
when the other two sinks arrive, as well as some of the faucet
handles. Volunteers finished the final electrical connections to the
grinder pumps for the septic system. They also installed the two
microwaves under the cabinets in the kitchen.

Philip
 

Wednesday, April 25, 2007

   The plumbers returned today. They repaired the pipe in the wall,
that the cabinet maker drilled into. They installed the sinks in the
men's restroom, one of the double sinks in the kitchen, and the under
the counter water heaters. Volunteers worked on electrical
connections and applying polyurethane.

Philip
 

Tuesday, April 24, 2007

   Volunteers worked on applying polyurethane to the window trim.
They also picked up the left over blocks around the building. The
tile workers returned today. They finished all the tile, they had
left out for the cabinets. They applied the grout around the showers,
and finished the remaining base boards. The tile is now complete.
Greg and Kevin started installing the counter tops, they completed the
tops in the infant room, nursery restroom, youth room, and several
pieces in the kitchen. They secured the counter tops any place that
their will be a sink.

Philip
 

Monday, April 23, 2007

   Greg and Kevin started installing the partitions in the men's
restroom this evening.

Philip
 

Sunday, April 22, 2007

   Joyce and Jennifer presented their final landscape design for
Baker Chapel today. They arrived before service to display their
poster designs and answer questions, for anyone who could not stay for
the presentation after church. They have designed and divided the
landscaping in three phases. The idea of three phases allows us to
proceed as the funds become available. They did a great job on both
the design and their presentation. They will both graduate in May
from Purdue University with a degree in Landscape & Horticultural
Design. They were given the task of designing the landscaping for
Baker Chapel, as their senior project. I hope that they get an A+.
These are two very fine young ladies, who really cared about their
project. Two of their family members came with them today as well.
Jennifer's mother Sharon, and Joyce's sister Jennifer. After their
presentation, we went to Baker Chapel, so they could see the progress
since they last visited. I also learned that they will be
participating in the same graduation ceremony as my daughter Maggie.
How great is that! I will get to see all three of them receive their
diploma's.

Philip
 

Friday, April 20, 2007

   The counter tops for the kitchen cabinets, youth room, and
restroom sinks were delivered today.

Philip
 

Thursday, April 19, 2007

   Carol and Gene applied polyurethane today. Sid finished the
receptacles in the kitchen. I helped Sid and Carl finish installing
the chandelier light in the foyer. Greg, Kevin and I worked tonight
in the women's restroom. We finished the partitions, installed on the
stall doors, latches, and coat hooks. This was quite a task. We were
determined to keep going until we had the women's side complete. We
worked until 10:25 p.m. We will still have some work to do in the
restroom, but the stalls are complete.

Philip
 

Wednesday, April 18, 2007

   Volunteers worked today applying polyurethane and cleaning up.
Sid installed the receptacles for the stoves in the kitchen. He also
started installing some receptacles in the island of cabinets in the
center of the kitchen. The microwaves and range hoods were picked up
today. Greg, Kevin, and I worked tonight installing the partitions in
the women's restroom.

Philip
 

Tuesday, April 17, 2007

   Greg, Kevin, and Spike worked tonight. They installed the trim
around the top of the stage floor. They also started to layout the
materials for the partitions in the restrooms.

Philip
 

Saturday, April 14, 2007

   Several of us helped with a BBQ fundraiser today. The proceeds
will help with the expenses of the youth mission trip to Colorado this
summer. For the last few years the Baker Chapel Youth group and the
Main Street UMC Youth group have been doing a combined mission trip.
They also do a lot of other activities together. Yesterday they
cooked 24 pork butts. Last night we pulled and BBQ them and placed
them in 1 pound containers. Today we grilled 48 slabs of ribs, and
over 100 chicken halves. We were sold out by a little after 12:00.
It rained most of the morning. Since we helped with the BBQ and
started at 6:00 a.m. this morning, no one worked at the church today.

Philip
 

Friday, April 13, 2007

   The cabinet maker returned today. He finished installing the
base cabinets in the kitchen, youth room, nursery, and nursery
restroom. He also installed more wall cabinets in the youth room and
the nursery. He accidentally drilled a hole in the water line behind
the wall in the women's restroom. They came and measured for all the
counter tops today. Two new cooking stoves and one new refrigerator
were delivered today.

Philip
 

Thursday, April 12, 2007

   The cabinet maker returned today with more cabinets. He started
installing the base cabinets in the kitchen. The partitions for the
restroom stalls were delivered today. The hanging light for the foyer
was picked up today. Volunteers worked applying polyurethane on the
completed windows. Greg started on the trim, that goes around the top
of the stage.

Philip
 

Wednesday, April 11, 2007

   Two volunteers worked today applying the final coat of
polyurethane on the two windows in the foyer. Seven volunteers worked
this evening. We helped the sound guy install and secure the large
speakers above the stage. He also worked on hooking up some of the
different units used in the sound system. Some of the ladies on the
decorating committee met at the church tonight to pick out the cabinet
counter top. Four of us then worked on installing the trim on the
window in the fellowship hall and the youth room. All of the windows
have been trimmed. We finished the last window at 9:15 p.m. We would
have finished sooner, but we had to perform surgery on the nail gun.

Philip
 

Tuesday, April 10, 2007

   Volunteers installed the conduit and electric wire from the
building to the septic pump. Others worked on applying polyurethane
to trim on the finished windows. Some more of the sound equipment was
delivered today. I did not realize that the cabinet maker also
installed the wall cabinets in the youth room yesterday.

Philip
 

Monday, April 9, 2007

   Two plumbers were on site today. They installed all of the
toilets and mounted the two water coolers on the wall in the hallway.
The cabinet maker delivered and installed, all of the wall cabinets in
the kitchen. Volunteers applied polyurethane to the completed
windows. Bob installed a trench for the electric from the building to
the sewage pumps. He also leveled some of the dirt on the south side
of the building. Kevin, Greg, Spike, and I worked tonight. We
installed the trim around the window in the nursery, and both windows
in the foyer. Spike installed some of the weather strips around the
double doors on the east side. Several people have written scripture
on the concrete floors. We announced in church a couple weeks ago,
that anyone could write their favorite scripture on the floor, before
the carpet is installed.

Philip
 

Saturday, April 7, 2007

   Bonnie and Debbie applied the second coat of grout sealer today.
Greg and I worked on trim this afternoon. We completed the trim on
the second window in the minister's office, the window in the office,
and the window in the infant room. We also removed the protective
masking tape from the windows that are completely finished.

Philip

 
Friday, April 6, 2007

   Six volunteers worked today. All Baker Chapel members. They
finished installing the pipe from the septic tanks to the mound
system. They finished some electrical connections and installed
receptacle covers. They filled the nail holes, and applied the final
coat of polyurethane on two window frames. Frank's reinstalled the
large vents that Carl painted. The company came and picked up the
electric lift today. This was the last piece of rental equipment. It
seems that I have an admirer who is a critic. Today I received my
second anonymous letter in the mail. First of all, I hope that as you
check the website daily for my grammar mistakes, that you are also
learning about Baker Chapel. Secondly, since you do not think enough
of yourself to supply a return address, I am responding to you with
this website. In my defense, I would like to say that most of the
time I do the progress report late at night, after working at least 12
hours or more, and attending one of many meetings in many volunteer
organizations in which, I am involved. Yes, I do make mistakes. I am
not perfect. Finally, I would like to point out that the letter you
sent on March 13; my name was misspelled and you had the wrong zip
code. In the letter you sent today; some of your corrections are
wrong. However, I do want to thank you for helping me with my
grammar. I only wish that you could correct me before I place in on
the website.

Philip
 

Thursday, April 5, 2007

   Bob worked on the water leak again today. He has repaired the
leak, and we now have a valve and water inside the building. He also
started installing the line from the septic tanks to the mound
system. Others worked on electrical connections, and applying
polyurethane to some trim.

Philip
 

Wednesday, April 4, 2007

   First of all, I wanted to give you a little more information
about the ladies from Terre Haute that have been helping this week.
Jeanne is a member of Emmanuel UMC and worked Monday. Pam and Kathy
are both members of Barbour Ave. UMC and worked Monday, Tuesday and
part of today. We hope they are blessed by blessing us with their
help. Today volunteers finished removing the high spots in the
expansion joints. Carol worked on the trim that has been installed.
She used steel wool to get a smooth surface, and filled the nail holes
in preparation for the final coat of polyurethane. They stained the
custom made receptacle covers for the window receptacles for the
candle lights. This covers were made by Jerry Lutz. They also
stained the last cross for the windows. Bob Gourley started working
on repairing the water line outside that developed a leak during the
freezing weather. When we installed the outside hydrant last fall, we
made the mistake of securing it with a steel post. When the ground
froze in January, the loose dirt raised up with the water line and the
post would not allow the hydrant to move. Therefore it placed things
in a bind and the pipe cracked. Kevin and I worked on trim tonight.
He had already completed the window in the classroom by himself before
I arrived. We also got one of the windows finished in the ministers
office.

Philip
 

Tuesday, April 3, 2007

   Two ladies returned to volunteer today from Terre Haute. They
helped clean the tile in the kitchen, men's and women's restroom, and
the restroom in the nursery. They also helped with clean-up. Other
volunteers helped to finish removing the high spots in the expansion
joints and install a light in men's restroom. They delivered the
remaining exit signs today, and they installed them as well. Tonight
Bonnie and I sealed the tile grout in the kitchen, men's and women's
restroom and the restroom in the nursery. Greg and Kevin worked
tonight and 'trimmed-out' the other two windows in the sanctuary.

Philip

 
Monday, April 2, 2007

   Three ladies from Terra Haute, Indiana volunteered at Baker
Chapel today. They cleaned, swept, and vacuumed several rooms. Carol
and Gene applied polyurethane to the trim pieces. Other volunteers
did some touch-up painting and installed the three drop ceiling lights
in the sanctuary. Tonight Greg P. and Kevin G. started installing the
trim. They trimmed out two windows in the sanctuary, the door-way to
the coat closet, around the open area window in the sound room, and
around the opening were the projector screen will be installed. The
trim looks great. It really sets off the windows, and the cross at
the top gives it a special touch.

Philip
 

Saturday, March 31, 2007

   The grills were fired up at 4:30 a.m. this morning. I arrived at
5:00 to help put the meat on. Jerol, Greg, Kevin and I helped at
various times with the BBQ fundraiser today. As I had mentioned
yesterday the money will go towards a new roof for South Friendship
GB church in Boonville. We cooked 96 slabs of ribs, 300 pork chops,
and almost 500 1/2 chickens. They served pork chop dinners, 1/2
chicken dinners, and pulled pork dinners. You could purchase single
chops, chickens, or pork butts. We used almost 50 gallons of BBQ
sauce. Some of the Baker Chapel ladies donated deserts. We had 12
big cookers and four small cookers. They had a lot of volunteers
help, and the deserts, baked beans and potatoe salad was all donated.
I had BBQ ribs for supper tonight and it was delicious. I worked at
home this afternoon. I worked at the church tonight applying the
final coat of polyurethane to several pieces of trim. When I left at
9:00 p.m. it was beginning to rain. We were supposed to have
scattered showers most of the day. God blessed us by holding the rain
away from the BBQ. I don't think anyone else worked at the church
today. But I forgot to mention that Carol and Judy worked on trim
yesterday. I began the day serving God by helping another church. I
thought it was only proper to end the day serving God at Baker Chapel.

Philip
 

Friday, March 30, 2007

   The tile workers applied the grout in the tile in the foyer.
They installed some tile border around the showers in the restrooms.
They put grout in the tile border in the restrooms as well. Jerol,
Carl and Harley volunteered today helping to cook 98 pork butts for a
fundraiser tomorrow. Tennyson General Baptist and Mt. Gilead General
Baptist are hosting a fundraiser tomorrow for South Friendship General
Baptist Church in Boonville. The proceeds will go towards a new roof
for their church. These same two church's held a similar fundraiser
for Baker Chapel last year. In southern Indiana we really don't pay
attention to different denominations among churches. If another
church needs help and we can do something to help others, we just do
it.

Philip
 

Thursday, March 29, 2007

   Tile workers worked in the foyer again today. They also did a
small area inside the second set of doors. Volunteers worked today
doing touch-up painting and working on trim. Six of us worked tonight
sanding, sealing, and applying polyurethane to some of the trim. Some
of the trim has all the needed coats. All of the trim has at least
been stained. Everyday is a day closer to completion.

Philip
 

Wednesday, March 28, 2007

   The tile workers applied the grout between the tiles in the men's
and women's restroom. They also cemented some of the tile down in the
foyer. The tile in the foyer is 12 in. X 12 in. and the tile in the
other areas is 16 in. X 16 in. The tile in the foyer is very time
consuming. Their will be two crosses inlaid into the tile floor.
This requires a lot of extra angles and extra cutting.

Philip
 

Tuesday, March 27, 2007

   The rest of the trim was delivered today. More sound system
supplies were delivered today. Volunteers have attached some of the
finished trim to the stage. The tile workers finished the tile in the
men's restroom, and did more layout work for the tile in the foyer
entrance.

Philip
 

Monday, March 26, 2007

   Four tile installers worked yesterday (Sunday) and finished
installing the tile in the kitchen. They worked again today. They
applied the grout between the tiles in the kitchen. They installed
most of the baseline, boarder tile in the men's and women's restroom.
They started cutting the tile for the foyer in the entrance of the
church. Volunteers worked applying polyurethane to the trim today.
This evening Greg, Kevin and Spike worked on trim. The rest of the
trim was delivered today. Their is a triangle piece of trim with a
cross attached that will go at the point of each of the windows.

Philip

 
Saturday, March 24, 2007

   While most people were enjoying the beautiful 80 degree spring
day doing something for themselves. Nine volunteers enjoyed the day
serving God at Baker Chapel. Under the direction of expert gutter
installer Jimmy Volz and his helper Zach Collins, along with Baker
Chapel members, they installed the remaining gutters and all the down
spouts today. They also applied polyurethane to several window
casings. They sanded some of the trim in preparation for the second
coat of polyurethane. Two paid tile installers, finished the women's
restroom floor, and started on the kitchen floor. These guys are true
craftsmen. Anybody who can take six floor tile and cut them into 36
pieces to craft them in a design around the floor drain, is in my
opinion "a craftsmen". We ending the day around 3:30, with the
pleasure of having served God.

Philip
 

Friday, March 23, 2007

   The correct number of volunteers from Epworth UMC in Indianapolis
is four men, and three women. They have been a big help the last two
days. They worked till 3:30 p.m. today before returning to
Indianapolis. They put the ceiling tiles back in the kitchen, stained
the rest of the trim work, applied sanding sealer to all the trim,
and started applying polyurethane to the trim. They finished
constructing the reading platform in one of the classrooms. They
installed more sound system wiring and cable. The gutter crew
installed the one piece, seamless gutter on the west side of the
building. They were then rained out, and had to quit.

Philip

 
Thursday, March 22, 2007

   Today, Baker Chapel welcomed at least eight volunteers from
Epworth UMC of Indianapolis Indiana. They along with some Baker
Chapel member volunteers, did a lot of work today. They installed the
outside lights by the front door, installed speaker cable and wire,
installed several speakers for the sound system in various rooms,
stained several pieces of trim, applied sanding sealer to a few window
casings, and constructed a reading platform in one of the class
rooms. They also installed a work counter (large shelf) in the sound
room. Wow, that was a long list. Four people installed floor tile.
They finished the floor in the men's restroom, and started on the tile
base board. They have the women's restroom floor 3/4 completed. The
tile company owner came and removed the tile in the kitchen. Then the
people who did not install the tile properly, came and removed all the
tile cement, by grinding and sanding. The materials for the gutters
were delivered today, and placed in the construction trailer.

Philip
 

Wednesday, March 21, 2007

   Greg stained some of the trim to be used around the windows
today. Kevin and Greg Greene worked several hours. They installed
the door handle hardware on two outside doors, closures on three
doors, and thresholds on two doors. They also started on the hardware
on the east-side double doors. Carl has spray painted two of the
large grills for the return air, in the heating system. A crew of
four worked this evening till 9 p.m. installing tile. This crew knows
what they are doing. They installed more tile in the men's restroom,
and have started on the women's restroom. Last night Kevin and Spike
removed all the ceiling tiles in the kitchen. When the floor tiles
are removed for replacement, they will have to grind the tile cement
off the floor. This will create a lot of dust. They removed the
ceiling tile, so they will not get dirty. More sound system supplies
were delivered today.

Philip
 

Tuesday, March 20, 2007

   Greg stained the last two window casings today. He also applied
sanding sealer to the four windows he stained yesterday. Sid
installed the boxes in the floor stage, for the sound system. A new
tile installation crew (three people) arrived at 4:30 p.m. today.
They started in the men's restroom. The decision has been made, to
remove the floor tiles in the kitchen. They will have to grind the
tile cement off the concrete floor, clean and install new tiles. The
tile company will pay for this re-work and the new tiles.

Philip
 

Monday, March 19, 2007

   Greg stained four window casings today. The wire and cable was
delivered for the sound system. Greg and Kevin met with the company
salesperson this morning,that we are getting the floor tile and carpet
from. We are not satisfied with the workmanship of the tile
installation. The purchase agreement included installation.
Therefore we are paying to have the tile and carpet installed. We
told them we wanted the tile installation to stop until this issue can
be resolved. The tile is not being installed properly.

Philip
 

Friday, March 16, 2007

   Three paid floor tile installers returned today. They installed
the tile in the laundry room and have installed almost all of the
kitchen floor. They are cementing the tile to the concrete floor.
After all the tile is installed they will put the grout in the grooves
between the tiles.

Philip
 

Thursday, March 15, 2007

   Jerol painted the finish coat of paint in the closet next to the
youth room. He installed the receptacle covers in the youth room.
Bonnie also helped. Three people started installing the floor tile
today. They installed the tile in the restroom next to the nursery.
They also did about 1/3 of the kitchen floor.

Philip
 

Wednesday, March 14, 2007

   Jerol painted the finish coat of paint in the youth room today.
Two people started on the tile layout on the floor in the kitchen.

Philip
 

Tuesday, March 13, 2007

   Jerol and Bonnie worked at the church today. They finished
taping the rest of the windows for staining. Installed insulation
around the remaining windows and the attic door. They swept the
floors were the tile will go. They painted the final coat of paint on
the west steel door.

Philip
 

March 12, 2007

   Greg and Jerol were the only volunteers today. They put the
second and third coat of paint on the double doors on the east side.
Two coats of paint on the steel outside door on the west side. They
did some touch-up painting around the air vent grills. Frank's came
today and installed the permanent thermostats and picked-up all their
ladders. The boards for the trim were delivered today. The tile,
grout, glue and supplies for the floors were delivered today.

Philip
 

Saturday, March 10, 2007

   Five volunteers worked this afternoon, all Baker Chapel members.
We did several different things. We added some braces in the steeple
base, finished the attic access doors, painted the second coat of
paint on two outside doors, applied the first coat of paint on the
(double) steel outside doors on the east side, attached the handles on
two exit doors, and one threshold on one outside door. It was another
beautiful spring day.

Philip
 

Friday, March 9, 2007

   Today was a beautiful sunny spring day. Temperatures reached 72
degrees. The frogs were singing, the wild turkeys scraping for bugs,
and the geese seemed confused as to which direction they should fly.
A man from the fire alarm company was on site today, installing the
alarm box and making wire connections. A few volunteers from Newburgh
were back again today. They began scraping the caulking that was
placed in the expansion joints. After it has dried, the caulking
needs to be scraped, so it is smooth with the floor. They also
stained two more window casings today. Someone mentioned to me last
week that it looked like we were about done with the church.
Although, everyday is a day closer their is still a lot of things to
do. The volunteers from Newburgh this week have been a big help.
Even though some of the things might have seemed small. They did
several things, and their help was a big step to being closer to
completion. We thank them, and may God Bless them, as they have
blessed us.

Philip
 

Thursday, March 8, 2007

   Volunteers from Newburgh and Baker Chapel continued working on
touch- up painting today. They also stained four more window casings,
and painted two of the outside steel doors. They installed the
fire/smoke alarm handles, that arrived yesterday. They sealed more
expansion joints in the concrete floor.

Philip
 

Wednesday, March 7, 2007

   Six volunteers from Newburgh UMC returned today. They continued
to seal the expansion joints until the ran out of caulking. They
finished sanding and taping off the rest of the windows. They are now
ready for staining. Frank's had a company come today to check and
adjust the air flow to all the vents today. They had previously
installed damper controls in the duct-work so they could change the
flow if they needed too.

Philip
 

Tuesday, March 6, 2007

   Several volunteers from both Newburgh UMC and Baker Chapel
worked today. They worked on sealing the expansion joints in the
concrete with foam and caulking. Sanding the window casings, and
stained two windows casings. They did touch paint in several areas.
They also installed some electric wire. Frank's heating installed the
remaining grills over the heat and air returns.

Philip
 

Monday, March 5, 2007

   Six volunteers from Newburgh UMC worked at the church today.
They applied another coat of paint to the men's restroom. They
repaired some small damaged areas to the drywall in several rooms.
They also sanded the window casings in preparation for staining. They
finished installing the insulation around the window edges, and
installed several receptacle covers. They were assisted by two Baker
Chapel volunteers.

Philip
 

Saturday, March 3, 2007

   Jerol was the only volunteer who worked today. He applied the
final coat of paint in the library. I think he was still a little
jittery (sp?) Sunday morning. I think he drank the whole pot of coffee
by himself. Jerol still remains a very dedicated angel volunteer to
this project.

Philip
 

Friday, March 2, 2007

   Volunteers finished installing the rest of the steel door
frames. They worked on connections for the fire/smoke alarms. They
hooked up the lights in the sound room. Most of the ceiling tiles
have been installed. A few have been left out to have access for
electrical connections and duct-work adjustments.

Philip
 

Thursday, March 1, 2007

   Six volunteers worked today. We traced down a missed electrical
connection. The receptacles were not working in the library. Sanded
the library walls in preparation for another coat of paint. They also
installed some of the emergency lights. Greg G. installed several
steel door frames. The telephone guy came to check into running the
underground wire back to the church. Heavy rain and winds this
afternoon.

Philip
 

Wednesday, February 28, 2007

   Volunteers installed the track lighting above the stage, and
hooked up the lights. They installed safety wires to the remaining
lights, and installed some of the emergency exit lights. Carl
finished painting the remaining door frames today. He said he painted
25 frames, with each frame having three pieces. Mid-west picked up
their lift and scaffolding today.

Philip
 

Tuesday, February 27, 2007

   Volunteers installed ceiling tile in the restrooms, closet and
kitchen. They also continued work on the fire/ smoke alarm system,
and making electrical connections. The restroom lights are complete.
Carl painted more door frames.

Philip
 

Monday, February 26, 2007

   Mike with Mid-west finished his work today. Volunteers finished
installing ceiling tiles in the hallway, nursery, office and
minister's office. They also worked on installing the fire/smoke
alarm system. Carl took more door frames home to spray paint.

Philip
 

Sunday, February 25, 2007

"With God ALL things are possible"
Matthew Chapter 19 verse 26

   The building committee announced today that this spring when the
weather permits. We will be moving forward, with the construction on
the multi-purpose building. This building will be attached to the
east side of the church. It will be over 6000 square feet. Include a
multipurpose area the size of a Jr. High gym. large youth room and
large storage room. It will also have a covered area in front for
unloading/loading in bad weather. This was on the original plans, but
we wanted to make sure we had funds available. We are once again
moving forward on faith. We are hopeful that we can construct the
shell and floor without exceeding our mortgage limit.

Philip
 

Saturday, February 24, 2007

   Today I met the J&J Landscape Design Company Inc. at the church
at 9:00 a.m. Just kidding!!!! I met with Joyce and Jennifer, two
Purdue seniors who are doing the landscape design for Baker Chapel.
It is their senior project. I can tell you that I am more impressed
by this two fine ladies, more than the first time I met with them.
They really care about this project. They had several sketches and
ideas, and many possibilities. About 12 people came to here their
ideas as well. We made a few suggestions. They left their sketches
for me to share with the congregation tomorrow. I also learned today
that yesterday was Scott's birthday. He said, the honor of placing
the cross on top of the steeple was the best birthday present ever.
Five volunteers worked today. Greg G. installed all the steel door
frames that had been painted. The rest of us worked on many different
areas. We traced some wires, to identify a missing electrical
connection. Sid and Jerol made the connection of the ground wire from
the cross. I patched some holes in the drywall (firewall) above the
drop ceiling. The building inspector noted we had to have these areas
completely sealed. We installed several ceiling tiles. All of the
ceiling tiles are in the infant room, adjacent restroom, youth room,
fellowship hall, and over half of the big hallway are complete. Greg
P. was the other volunteer today. He installed several of the above
mentioned tiles. I went to town today for lunch, and attended another
church this evening as a fundraiser for a needy family. At both
places many people saw the steeple go up on the evening news last
night. It is the "talk of the town" how nice it looks.

Philip
 


Friday, February 23, 2007

   Volunteers installed a couple door frames and worked on
electric. The steeple arrived at about 9:30 a.m. The crane arrived
at 10:00 a.m. At 11:00 a service for "The Consecration of The
Steeple" led by Rev. Randy Anderson, was held in the sanctuary. Over
75 people attended this service. The cross that goes on top of the
steeple was brought into the sanctuary for this service. Those
attending the service could write their name (with a marker) on the 4
ft. long tubing that connected the cross with the steeple. The
steeple was transported on a trailer laying down. The top of the
steeple pointed forward on the trailer. The crane was secured to the
top of the steeple. The steeple was on a large hinge pin and as the
crane lifted up the trailer slowly moved forward. This caused the
steeple to stand upright. The hinge pin was removed and the steeple
hung freely from the crane. The bottom skirt was bolted to the
steeple. Before the steeple was lifted, Bonnie Watson had requested
that we write a scripture inside the steeple. I wrote John 3:16 "For
God so loved the world that he gave his one and only Son, that whoever
believes in him shall not perish but have eternal life." The steeple
was placed on the base at 1:10 p.m. The holes were marked for the
bolts. The steeple was removed to drill the holes for the bolts. The
steeple is secured with eight 5/8 long threaded rods. The steeple was
placed back on the base and bolted. Once the bolts were tightened,
the crane was unhooked. The crane was then hooked to a basket. Scott
Brewster was selected to go up in the basket to attach the cross.
Scott first placed the connecting tubing into the steeple. At 2:50
p.m. the cross was set into place. When this took place the remaining
people in attendance clapped, and those watching from their vehicles
honked their horns. It is hard to describe in words the inner feeling
of seeing this take place. This steeple is beautiful. The base of
the steeple is 7 feet 8 inch square. The skirt that was added to the
bottom is 13 feet wide.The steeple base is 38 feet from the ground.
The steeple is 29 feet 4 1/2 inches tall. The cross is 5 feet tall,
with the cross member being 2 feet 2 inches wide. Their is a 12 inch
lightning protection rod on top of the cross. You can do the math and
see that the tip of the rod is over 73 feet from the ground. Pictures
will be available on the website soon.

Philip

Thursday, February 22, 2007

   Kevin, Greg G. and Greg P. finished preparing the steeple base.
Mike installed more ceiling tiles around the borders. Carl painted
more door frames. Volunteers worked on electrical connections and
clean-up.

Philip
 

Wednesday, February 21, 2007

   Kevin and Greg Green started the final preparations to the
steeple base. The steeple is scheduled to be delivered and installed
Friday of this week. They also installed trim work around the attic
access doors, and started to shim the windows. Sid and Jerry made the
final connections to some of the lights in the sanctuary. Mike has
finished most of the ceiling frames. He will install ceiling tiles
around the border of every room. After inspection, volunteers will
install the remaining tiles.

Philip
 

Tuesday, February 20, 2007

   Mike installed the ceiling frames in the men's restroom and
finished the sound room frames. Volunteers wired the lights in the
library, nursery, infant room and restroom next to the nursery. Carl
took some of the steel door frames home to spray paint.

Philip
 

Monday, February 19, 2007

   Brock finished spraying the walls in the sanctuary last night.
Mike installed the ceiling frames in the women's restroom, and started
on the sound room today. Volunteers wired the lights in the youth
room, and storage room. Kevin painted the inside of the bulk head in
the sanctuary this evening. The library still needs a coat of paint,
and several areas need touch-up work, and the painting will be
complete.

Philip
 

Friday, February 16, 2007

   Mike from Midwest installed the ceiling frames in the nursery,
infant room and the restroom next to the nursery today. Volunteers
worked on securing lights with wires attached to the ceiling. This is
a code requirement in case of an earthquake. The steel door frames
for the inside doors were delivered today. Franks Heating worked on
connecting duct-work to the vents and registers. I stopped by the
church tonight at 9:30 p.m. and Brock Holder was applying the finish
coat of paint to the sanctuary walls.

Philip
 

Thursday, February 15, 2007

   Volunteers wired the lights in the fellowship hall today. They
also installed some switches and receptacles.

Philip
 

Wednesday February 14, 2007

HAPPY VALENTINE'S DAY


   Workers finished installing the ceiling frames in the fellowship
hall. They also did the ceiling frame in the youth room and the
office. Volunteers wired the lights in the hallway.

Philip
 

Tuesday, February 13, 2007

   Mike and Ben started installing the drop ceiling frames in the
fellowship hall today. They also did the frames in the
mechanical/closet next to the youth room. Three workers from Frank's
Heating started installing the vents and connecting to the duct-work,
in the ceiling grids in the areas that are completed. Jerry and Sid
wired the light in the pantry, several receptacles, and started on the
lights in the hallway. It rained most of the day, turning to freezing
rain, then snow after dark.

Philip
 

Monday, February 12, 2007

   Mike and Ben from Midwest worked on the ceiling frames today.
They finished the hallway, did the pantry next to the kitchen and the
closet in the fellowship hall. Volunteers wired the lights in the
classroom and minister's office. Today is Logan's 18th birthday!!!!

Philip
 

Saturday, February 10, 2007

   Six volunteer's worked today. We scraped drywall mud from the
floors, swept, cleaned, and vacuumed. We moved everything out of the
fellowship hall, and put some of the things that are not needed, in
the storage trailer.

Philip
 

Friday, February 9, 2007

   Mike with Midwest worked today. He started installing the drop
ceiling frames in the big hallway. Volunteers worked on installing
the lights in one of the classrooms, and the minister's office. Brock
Holder and his helper John came this evening under the cover of
darkness. They are scheduled to work Sat. at their "real paying
jobs". So they worked at the church tonight. They painted the closet
in the fellowship hall, coat closet, sanctuary ceiling and the
sanctuary walls. They painted several gallons of paint. These guys
are a real blessing to Baker Chapel.

Philip
 

Thursday, February 8, 2007

   Three drywall finishers worked today. They textured the walls in
the sanctuary and finished the sound room. Except for a few small
areas in a couple closets, most of the drywall mud-work is complete.
They also installed the drop ceiling frames in one classroom and the
minister's office. Volunteers installed lights in the kitchen,
classroom, office, and more receptacles. The kitchen lights are
connected and hooked to the permanent light switch. Volunteers
continue to clean-up on a daily basis.

Philip
 

Wednesday, February 7, 2007

   Two drywall finishers worked today. They textured the ceiling in
the sanctuary. These guys are workers from Midwest Construction.
They will also install the frames for the drop ceilings. They
installed the drop ceiling frames in the kitchen. Several boxes of
ceiling tiles were delivered today. Electrical volunteers started
installing receptacles in areas that the painting is complete.

Philip
 

Monday, February 5, 2007

   Six volunteers from Tri-State Painting painted today. Other
Baker Chapel volunteers helped paint and clean-up. One drywall
finisher worked today. The interior design committee met with the
carpet guy this evening. They finalized what colors go where, and
took measurements.

Philip
 

Saturday, February 3, 2007

TODAY WAS PAINT DAY!!!!!!!!!!!!!!

   Today, volunteers began painting at Baker Chapel. Cletus Miller,
Gene Feagley and Brock Holder are three angels from God. These guys
are professional painters. They have volunteered their time and
equipment. They are using airless electric sprayers. The three of
them along with nine other volunteers, all Baker Chapel members began
painting at 8:00 a.m. today. They applied two coats of paint in the
ministers office, work office, 2- classrooms, mechanics room,
kitchen , narthex, and fellowship hall. They also applied one coat in
the foyer and the men's restroom. They sprayed and rolled on over 100
gallons of paint today. I was unable to help today. Logan and I
attended the Purdue Ag Alumni Fish Fry in Indianapolis today. We had
the privilege to here The story of Apollo 13. The guest speakers were
Captain James Lovell, Apollo Astronaut Commander and Gene Kranz,
former NASA Director of Mission Operations. In Captain Lovell's
speech, he stated that their are three kinds of people in the world.
First, "Those people who make things happen". Second, "Those people
who watch things happen". And third, "Those people 'who ask' What
happened"? Today, the people who volunteered, are people who "Make
things happened". We continue to be blessed.

Philip
 

Friday, February 2, 2007

   Two drywall finishers worked today. They sprayed the splatter
finish on the walls and ceiling in the front entrance. Volunteers
worked at moving items around and covering them with plastic, for
protection while painting. They also did clean-up work. We are
hoping some volunteers come to help paint tomorrow.

Philip
 

Thursday, February 1, 2007

   One drywall finisher worked today. He started applying the
texture on the ceiling in the sanctuary. He completed the bulkhead
around the outside edge of the sanctuary. Several gallons of paint
and supplies were delivered today. Their are seven different colors
including the primer.

Philip
 

Wednesday, January 31, 2007

   One drywall finisher worked today. Volunteers covered some of
the electrical boxes with paper and tape. This is being done to
protect them, when we start painting. The paint with be sprayed on.
We will paint one coat of primer, and two coats of paint. Last Sunday
the congregation voted on their choice of color schemes. We have
chosen the colors of paint and carpet for the hallway, fellowship hall
and the sanctuary, and the tile for the entrance. The decorating
committee will choose the remaining paint colors.

Philip
 

Tuesday January 30, 2007

   Two drywall finishers worked today. Volunteers finished covering
the windows and doors with plastic. They delivered some of the frames
and supports for the drop ceilings today. Volunteers continue to
sweep and vacuum up the drywall dust.

Philip
 

Monday, January 29, 2007

   One drywall finisher worked today. Volunteers worked on covering
the windows and window frames with plastic. This was in preparation
for painting. Which we hope to be able to start on next week.

Philip
 

Saturday, January 27,2007

   Today I met two fantastic people. Joyce and Jennifer are both
seniors at Purdue University. They will graduate in May with a degree
in Landscape & Horticultural Design. They have been chosen by God,
and then chosen by their Professor to design the landscaping at Baker
Chapel. Several weeks ago I was contacted by two different people
about a program, that Purdue Professor Dr. Michael N. Dana was looking
for community landscape planting projects. I submitted Baker Chapel
as a possible project, and we have been selected. I had the joy and
pleasure to meet Joyce and Jennifer in person today. They are two
very fine young ladies who are eager to help with our project. We
were scheduled to meet at the church at 8:00 a.m. this morning. When
I arrived at 7:50 a.m. they were already taking pictures. I spent
time with them walking the grounds, going over blue prints of our
construction, and sharing ideas from members of their suggestions.
Greg also came this morning and spent time answering their questions
and giving them a tour of the building. I left for a while to attend
another meeting. Logan helped them take soil samples and assisted
them until I returned. Gary Michel, our County Extension Educator
came today to meet them as well. We went and did an inventory and
identified the trees that has been donated to us in Sept. from
the "New York Says Thank You Foundation". This trees have been
winterized and protected until we were prepared to plant them. Joyce
and Jennifer had many questions. They truly seem excited and eager to
help with the project. We all went to lunch in town. Gary jumped at
the chance for me to buy him and the others lunch. I felt that was
the least I could do. Gary was one of the people who contacted me
about this program. The other person who contacted me was Larry
Ordner. Larry is the Regional Director for our U.S. Senator Richard
Lugar. A special thanks to both of you for sending me the
information. After lunch, we returned to the church to discuss the
possible time-line for their work. And the process that they will be
following. The Boonville FFA chapter, as well as the local Master
Garden club has volunteered to help with the planting of the
landscaping. This evening Greg met with the person who is going to
paint the church, and to develop a schedule.

Philip
 

Friday, January 26, 2007

   Two drywall finishers worked today. They continue to work in the
sanctuary. While the joint compound dries in the sanctuary, they
apply the final coat and do sanding in other areas. Jerry Lutz has
hand crafted a cover plate for each of the receptacles, for the window
candles. They are made of popular wood to match the window frames. I
have not seen them yet, but I have been told they are beautiful, and
look perfect. I am sure it took him many hours. Thank you Jerry.
Others continue to wipe dust from the walls, and vacuum the floors.

Philip
 

Thursday, January 25, 2007

   One drywall finisher worked today. Volunteers installed two
pull-down access stairs. One in the storage above the classroom, and
one in the utility closet.

Philip
 

Wednesday, January 24, 2007

   Two drywall finishers worked today. They have been applying
compound in the sanctuary, and the final coats in other places. The
following areas are ready to paint conference room, ministers office,
main office, restrooms and kitchen. Volunteers finished the boxes and
receptacles in the window sills. They also continued to clean walls
and scraping floors. The telephone guy was here most of the day
installing the phone lines.

Philip
 

Tuesday, January 23, 2007

   Two drywall finishers worked today. Volunteers worked on
sweeping, vacuuming, and wiping the dust from walls. Others started
installing the electric boxes and receptacles in the window sills for
the candles.

Philip
 

Monday, January 22, 2007

   Two drywall finishers worked today.

Philip
 

Friday, January 19, 2007

   Two paid drywall finisher's worked again today. The fellowship
hall, big hallway, nursery, infant room, adjacent restroom, youth
room, and one of the class rooms are complete and ready to paint.
When the joint compound is sanded, it creates a lot of dust. We will
not begin painting until all the drywall finish work is complete. The
drywall will then have to be wiped free of the dust. I also need to
make a correction. We have 14 windows and 14 candles (not eleven) and
12 of these have been paid for as a specific donation, such as a
memorial, or in honor of someone. Volunteers today, removed all the
items from the sanctuary, in order to have easy access to finish the
drywall. They also started on the sanctuary ceiling today. Most of
the areas requires three applications of joint compound, then requires
sanding.

Philip
 

Wednesday, January 17, 2007
Thursday, January 18, 2008

   Two paid drywall finisher's worked each of these two days. They
are making progress.

Philip
 

Tuesday, January 16, 2007

   Four volunteers worked today. They installed cable in several
rooms. This cable could be used for TV monitors in the future. We do
not have plans to install the monitors right away. However, it is
easier to run the cable now. They also removed all the items out of
the kitchen and supplies that were stored in one of the classrooms.
They moved them to a different room, to allow the drywall finisher
easier access. One drywall finisher worked today. We had a few snow
flurries today, and the temperature is supposed to drop to 17 degrees
tonight. Frank's has most of the duct-work installed. They probably
won't work again until we have the drop ceilings installed.

Philip
 

Monday, January 15, 2007

       RAIN ! RAIN! RAIN!

   Heavy rains last night and most of this morning. It then lightly
rained most of the day. We have had 4 inches of rain since last
Friday. Two drywall finishers worked today. They sprayed the texture
on the walls in the fellowship hall and the big hallway. They used a
air powered sprayer to "splatter the walls" then smoothed the edges
with a trial. The "candle lights" for the windows arrived at the
church today. Each of the eleven windows will have a candle in the
center, placed on the window sill. We pre-wired under the sill and
the lights will fit directly into a special electric socket.

Philip
 

Saturday, January 13, 2007

   The ladies on the decorating committee met at the church this
morning. They had some larger carpet samples, they think they have
selected the colors. Some of them went to get some paint samples this
afternoon to match the carpet. I was the only one that worked at the
church this afternoon. I framed in, and installed two doors in the
attic. They are small access doors through the firewall. That way if
we need to get access in the attic, we can get to both sides. It
rained all day today. They are predicted heavy rains for tomorrow.
As I was picking up my tools preparing to leave. Carl and Dorothy
came to walk around inside the church for exercise, out of the rain.

Philip
 

Friday, January 12, 2007

   The drywall finisher worked today. At almost quitting time three
other finishers came to help him, and brought some scaffolding. I
think they just wanted to get a good look at the place, some of them
might be helping him next week. It rained most of the day.

Philip
 

Thursday, January 11, 2007

   The drywall finisher worked today. Frank's worked on duct-work.
They came and picked up the other outside lift today.

Philip
 

Wednesday, January 10, 2007

   Volunteers made the final water connections to the church
building. They removed the temporary water hydrant by the meter next
to the road, and covered the pipe after the connections were
complete. They came and got the large outside basket lift today, and
are supposed to come get the second one as well. We might need to
rent one again, when we set the steeple. However, with a rental cost
of $100 per day on just the one big lift, we did not need these two
machines to just sit here till we set the steeple base. Frank's
installed duct-work, and one paid drywall finisher worked on the
drywall. We have returned some of the electrical supplies that were
ordered, that were not needed.

Philip
 

Tuesday, January 9, 2007

   Today was a copy of yesterday, only it was a lot colder today
with occasional snow flurries.

Philip
 

Monday, January 8, 2007

   Frank's installed duct-work today. Believe me when I say their
is "a lot of duct-work". One paid drywall finisher worked on
installing tape and joint compound. He makes good progress for one
person. Kevin and Greg are working on getting prices on some of the
things that need to be completed next.

Philip
 

Saturday January 6, 2006

    Seven volunteers worked at different times this morning. Three
of us worked till 3:00 p.m. We put insulation around the front door,
and the double door on the east, and trimmed these two doors with
drywall. We re-shimmed the double doors. We framed in the
video/projector screen opening too a smaller size, and installed
drywall. The person who is doing our sound/video system changed the
dimension on the opening. All of the drywall is now installed. We
removed some of the temporary wiring in the attic and attached some
bracing. We pulled the lift out of the mud onto the gravel parking
lot.

Philip

 
Friday, January 5, 2006

Hallelujah!

    Volunteers finished installing the vinyl siding on the east side
today. The vinyl siding is complete!!!!!!!!!!!!!!!!!!
They finished about 2:00 p.m. right before it began raining. One of
the lifts is still stuck in the mud but the siding is complete.
Frank's worked on duct-work. The drywall finisher worked again today.
The east side is where the gym will eventually connect. We are
currently having a pledge drive with-in Baker Chapel membership. We
are also getting quotes and firm prices on the different things needed
to finish the church. Until we get firm prices to get a handle on our
finances, we are not sure if we have the current funds to start on the
gym. When the gym is built the siding can be removed and placed on
the east end of the gym. We went ahead and installed the siding so
the building could be sealed for winter.

Philip
 

Thursday, January 4, 2006

    Volunteers finished installing the vinyl siding on the south side
today. They also started on the east side and got about 1/3 of it
installed. Frank's installed duct-work. One paid drywall finisher
worked again today. Pastor Russ Able (spelling ?) of Mt. Vernon UMC
came today and brought with him about 15 very hard working youth.
They were members of their youth group. They clean-up, carried trash
to the dumpster and helped install siding. They did a great job. It
started raining in the late afternoon.

Philip
 

Wednesday, January 3, 2007

    Volunteers almost finished installing the vinyl on the south side
today. They only have about 8 more rows in the very top. It got
dark and they were unable to finish. Frank's installed duct work.
One paid drywall finisher started taping joints and applying joint
compound today.

Philip
 

Tuesday, January 2, 2007

HAPPY NEW YEAR!

    Volunteers installed vinyl siding on the south side today. The
south side is almost 1/2 completed. Frank's worked on installing duct
work. It was a nice sunny day. It was announced in church Sunday
that Mt. Vernon UMC has sent us a nice donation. Thank you very
much. They have given us a lot of support, by also sending volunteers
to help. They installed a lot of the fiberglass insulation in the
ceiling.

Philip
 

Saturday, December 30, 2006

     SHAZAM!!!!!!!!!!!!!

     It was a GREAT progress day at Baker Chapel today.  Fifteen 
volunteers worked today.  They were all Baker Chapel members except 
for one, that was Gary Michel.  Most of the volunteers worked on vinyl 
siding.  We finished installing the siding on the side walls of the 
front (north side).  We installed siding on the entire west side.  We 
have put the corners, starter strips, and a few pieces of siding on the 
south side.  Others finished installing the drywall on the walls in 
the front entrance and the ceiling in the classroom that will have the 
storage above.  We got one of the outside bucket hoists stuck in the 
mud.  I went and got a big tractor and we pulled it out.  They got 
the other lift stuck later in the day, and it had to be pulled out as 
well.  We will leave the tractor on site until we finish the siding.  
Just for curiosity, I took a scales to church today and weighed a 
sheet of drywall.  One 4ft X 12ft sheet weighs 110 pounds.  I was glad 
I waited until we were almost finished with drywall too find out how 
much they weigh.  Several ladies spent a lot of time today, trying to 
pick out some flooring material at the church.  They have narrowed the 
list and will get larger samples, then review their decision.  I 
think they are going to have a few choices and let the congregation 
make the final decision.  The Buxton's provided a nice hot lunch of 
soup and hot dogs today.

Philip

Friday, December 29, 2006

     Volunteers worked outside today, under bright sunny skies.  They 
finished the vinyl siding around the front entrance.  They installed a 
2ft. X 2ft. vent in the wall, and installed the vinyl siding around 
the vent.  They put the expandable foam insulation and trimmed around 
the outside steel door in the fellowship hall.  Installed the lights 
in the ceiling of the classroom storage area.

Philip

Thursday, December 28, 2006

     They delivered 14 sheets of drywall today.  This should be enough 
to finish things.  Six volunteers worked today.  They finished 
installing the drywall on the ceiling in the front entrance.  
Celebrate!  Celebrate!  All of the double layer drywall is installed 
on the ceilings.  They installed the floor joists and the sub floor in 
the utility room for over head storage.  Installed the floor in the 
storage room above the classroom.  They used expandable foam 
insulation around the two steel outside doors in the sanctuary.  They 
also trimmed around these two doors with drywall.

Philip 

Wednesday, December 27, 2006

     Ten volunteers worked today.  Two worked on electric and the rest 
worked on drywall.  They finished installing the drywall in the 
sanctuary.  They started installing drywall on the ceiling in the 
front entrance.  The rental company delivered a boom/basket lift 
today.   We also returned the big outside lift.  The boom lift will 
work better in the mud for installing the vinyl siding.  Frank's 
Heating is working at night time.  This way they can use the electric 
lifts that we have rented for the inside work.

Philip 

Tuesday, December 26, 2006

    They delivered 80 sheets of drywall today.  Eleven volunteers,
all members of Baker Chapel worked today.  We finished installing the
drywall in the sound room.  We finished installing the drywall on the
ceiling of the sanctuary. FANTASTIC!!!  We installed more drywall on
the bulk head around the top of the sanctuary ceiling.  More heating
and air supplies were delivered today.  Frank's installed duct-work.
All three of the heating units are now functional.

Philip
 

Sunday, December 24, 2006

     Tonight 119 people were at Baker Chapel for the candlelight
service.  After someone mentioned during Praises, that they were
thankful for all the young people present.  Preacher Mike asked those
in attendance who were under the age of 18 to come forward if they
felt comfortable doing so.  Twenty-two young people came forward.  As
they held hands everyone prayed for these young people, as they are
the future of Baker Chapel.  We had a few music specials.  It was
quite impressive as the lights were turned off, and everyone held
their burning candle, as we sang Silent Night.  Even more impressive
was Cindy Shelton giving a silent praise (sign language) to a CD with
singing of Silent Night.  At the very end, after being moved to tears,
I began singing out loud "Surely the Presence of the Lord is in this
Place".  Mainly because, HE WAS!!!
Everyone joined in as we sang it two times.  It was a very nice
service.  I would like to personally wish each of you a Merry
Christmas.  And may we remember the birth of our Christ Child everyday
through out the year.

Philip
 

Saturday, December 23, 2006

     Only four volunteers today.  We did not work very long.  We
leveled some rock in the parking lot.  Did some cleaning up and
sweeping in the church.  Installed some temporary wiring for some
outside lights.  We are having a 7:00 p.m. Christmas Eve service at
the church.

Philip
 

Friday, December 22, 2006

     Nine Baker Chapel members volunteered their time and talents
today.  They installed the last outside door in the sanctuary on the
south wall.  They installed drywall on the ceiling in the sanctuary. 
They have the ceiling about 1/2 completed.  They used all the drywall
that was on site.  They also did some general clean-up.  A load of
rock was delivered and spread today.  The parking lot was starting to
get muddy from all the rain, and where we trenched in the water line
last week.

Philip
 

Thursday, December 21, 2006

     Seven volunteers worked today.  They finished installing the
drywall around the inside of the bulk head above the stage.  The sound
system guy was here today letting us know what was needed in
electrical and wiring access in the bulk head.  We can now remove the
electric lift, that was on the stage for the ceiling installation. 
Frank's worked on duct work.  It rained most of the day.

Philip
 

Wednesday, December 20, 2006

     The front doors, and the second set of doors into the church were
delivered and installed today.  These doors cost several thousand
dollars, and they were installed by the company that we purchased them
from.  About eight volunteers worked today.  Jerry Lutz from Boonville
helped Sid with electrical connections.  Volunteers finished framing
around the last two heat vents in the sanctuary.  Mark that job off
the list!  They also installed the two vinyl corners and the starter
strip on the front section, around the new doors.  Gene has returned
to working at the site, and his arm is doing really great.  Frank's
worked on duct work.

Philip
 

Tuesday, December 19, 2006

     Few volunteers today.  They installed a few more pieces of
drywall in the entrance and cleaned up.  A couple of people worked on
electric.  Frank's worked on duct work.  They also have the heating
unit that services the sanctuary hooked up and working.  This will
make it more pleasant when we have Christmas Eve service in the new
building.  Greg, Spike, and Kevin were already working this evening,
when I arrived at 6:30.  We finished installing the drywall on the
ceiling, inside the bulk head above the stage.  We started the drywall
on the bulk head.  We worked until 10:00 p.m.  Every thing that is
finished makes it one step closer to completion.  One of the guys
tonight stated "All we have to do is finish."

Philip
 

Monday, December 18, 2006

     Another 100 sheets of drywall was delivered today.  Bob Gourley
installed the septic tanks today.  Frank's hooked the gas lines up to
the two outside units on the west, and the electric to one of the
units.  Baker Chapel volunteers installed the insulation in the
ceiling in the front entrance area.  They also started on the drywall
in the entrance.  Greg P., Kevin, Spike and I worked this evening till
10:15 p.m.  We installed drywall on the ceiling in the sanctuary. 
Just like the rest of the building, fire code requires two layers of
drywall on the ceiling.  It is a slow process, plus we have to cut out
for all of the recessed lights.  Greg got the lumber for the floor
joists of the storage area above the utility room.

Philip 
 

Sunday, December 17, 2006

     Gene Green was in church today.  He said his arm is doing OK.  It
really never did hurt much.  Greg Perigo, my son Logan, and I
installed vinyl siding at the church today.  Greg worked by himself
for almost three hours before Logan and I arrived.  With the help of
the parking lot lights.  We finished all the siding on the north walls
shortly after dark.  If you look at the church from the north (front)
the siding looks complete except for the front wall that has the front
door opening.  We cannot install siding here until the front door is
installed.  Yes I know, you are not supposed to work on Sunday, but
their is a chance of rain the next three days.  Besides, working on
God's church isn't work anyway, it is a joy!

Philip
 

Saturday, December 16, 2006

     The total number of volunteers today reached thirteen.  We were
all members of Baker Chapel.  Bob Gourley and the boys (Derek, Jacob
and Logan) trenched and installed the gas line connecting all of the
units and the water line from the road to the church.  They did not
have all the required fittings to complete the line connections but
the pipe is in place.  Other volunteers installed some of the outside
steel doors.  They installed the one in the fellowship hall, one of
the doors in the sanctuary, and the double door on the east side next
to the proposed gym.   Everyone else worked on installing vinyl
siding, and the boys helped with this also.  They worked mainly on the
north side (front) and a few pieces on the west side. They also picked
up and organized the left over blocks and cap stone, and cleaned up
outside.  The Shelton's provided a great lunch of vegetable soup,
cornbread (correction, awesome cornbread) and cake for desert.  I know
I have said this before.  As the last of us left after dark, the
building looks great in the silhouette of the lights. The pure white
vinyl simply shines and the windows sparkle.  The most fantastic
thing about today is that three high school boys (correction,
young men) gave up most of their Saturday to work on God's church.

Philip 

Friday, December 15, 2006

     A small number of Baker Chapel volunteers installed vinyl siding
today.  They got several square feet installed.  It was a beautiful
sunny day, reaching temperatures of close to 60 degrees.  Frank's
installed more duct work.  Kevin and I worked this evening.  Kevin
worked on framing around the individual duct vents in the sanctuary. 
I finished installing the drywall in the laundry room.  We worked till
10 p.m.  We left tired, but satisfied in serving our Lord.

Philip

Thursday, December 14, 2006

     The usual small number of Baker Chapel regular workers
volunteered today.  They finished the framing of the bulk head in the
sanctuary.  Installed some drywall in the coat closet.  Frank's worked
today installing duct work.  We had our first major accident today,
since construction began.  A member of Baker Chapel (Gene Green) had a
mishap with a nail gun today.   The nail went into his arm several
inches, and stopped at the head of the nail.  It went length wise with
his arm, missed all bones and arteries, thank God.  Gene is retired,
but has put many hours of volunteer work in at the church.   We pray
for a complete, and speedy recovery.

Philip

Wednesday, December 13, 2006

     Frank's Heating worked today installing duct work.  Volunteers
worked on building the bulk head above the stage in the sanctuary. 
This is for lighting and sound system.  Three of us worked tonight
till after 9 p.m.  Kevin and Spike installed tape and joint compound
on the ceiling and the walls of the storage room behind the stage.  I
finished the wall in the plumbing chase area.  I also worked on other
small areas (one man jobs) finishing small areas with drywall.

Philip

Tuesday, December 12, 2006

     Yesterday they came and emptied our large construction dumpster. 
I am sure that this was the first time it has been emptied since we
began construction.  That just proves that our volunteers, are very
caring people and have not wasted very much.  Volunteers started
installing the drywall on the ceiling in the room behind the stage
wall.  Four of us worked this evening.  We finished the ceiling that
the workers started today.  We also finished installing the drywall on
the walls.

Philip

Monday, December 11, 2006

     Frank's Heating worked today.   Very few volunteers.  They
installed a few pieces of vinyl.  I reported last week that the paid
block layers had finished all the block and the cap stone.  Carl
reported in church yesterday, that when he told the block layers the
address, so they could mail us the bill.  Their response was "what
bill".  These people were hired to finish the block.  They decided, 
they would just donate their time.  We continued to be blessed.

Philip

Friday December 8, 2006
Saturday December 9, 2006

     The outside heating and cooling units were delivered early Friday
morning.  They had to be unloaded and set in place by using a crane. 
They did this very early while the ground was still frozen.  I was out
of town on business Friday and Saturday.  Therefore I cannot tell you
what was done each day, but I can tell you what took place over the
two day period.  Volunteers applied drywall tape and finish compound
to the top four feet in the chase area behind the restrooms.  They did
this area, so they could remove the scaffolding boards that were used
to work in this area.  They finished installing the drywall on the
south wall of the sanctuary.  They started to install the drywall on
the ceiling in the sanctuary.  The installed the floor joists, and
some of the sub floor in the second story storage area above one of
the class rooms.

Philip 

Thursday, December 7, 2006

     Wow!  Let me tell you that those three guys from Avon UMC know
how to slap on drywall.  The three of them along with other volunteers
finished the drywall in the men's restroom, the hallway between both
restrooms, and the walls in the nursery.  The gas company installed
the gas line from the highway back to the church today.

Philip

Wednesday, December 6, 2006

     The electric company unhooked the temporary service today and
hooked up the permanent service.  We now have permanent electric
service inside the building.  The block layers returned today and
finished the block and the cap stone.  Volunteers finished installing
drywall in the utility room between the restrooms, constructed the
wall at the end of the shower in the men's restroom, and covered with
drywall.  Some of the electrical receptacles are now live with
electricity.

Philip
 
Tuesday, December 5, 2006

     They delivered another 100 sheets of drywall today.  Volunteers
finished installing drywall on the ceiling in the men's restroom and
the walls in the women's restroom.  They installed some of the
electrical receptacles in the boxes.

Philip
 

Monday, December 6, 2006

     Volunteers worked on installing drywall on the walls in the
women's restroom.  They also added some electrical boxes in a few
areas where we thought we needed them.  They delivered the five
outside steel doors and frames today, except for the front door.  Ron
DeVaisher from Avon UMC has returned this week for the third time.  He
also has with him the tag team of Don and Don (sorry don't know their
last names).

Philip
 

Sunday, December 3, 2006

     Baker Chapel had a float in the Boonville Christmas parade
today.  It was a cold but mostly sunny day.  Thirty one members
either rode on the float or walked along side giving out candy canes.
Each candy cane was attached to a piece of paper with "The meaning of
the Candy Cane". [Many years ago a candy maker wanted to make a candy
that would symbolize the true meaning of Christmas - "Jesus".  The
hard candy was shaped like a "J" to represent Jesus' name.  The color
white stands for the pureness of Jesus.  The color red represents the
blood Jesus shed for us.]  On the other side of the paper it stated:
Baker Chapel says Thank You for your support!!  And listed are current
location and times of our Sunday Services.  We gave away over 2500 of
these candy canes.  Some of those that rode on the float threw out
other candy as well.  Three members carried a large banner in front of
the float which read Baker Chapel Says Thank You.  And "Faith Is
Stronger Than The Storm".  The back drop of the banner was a current
picture of the church under construction.  On the front of the truck
pulling the float was a poster titled  "Jesus Rocks".  On the float
were kids dressed in costume, of the Nativity Scene.  A sign on each
side of the float read," A New Life--A New Beginning".  A large vinyl
poster 6 feet X 9 feet facing the front had a picture of the church as
it will look when completed.  Another poster on the back stated "Jesus
is the Reason for the Season".  As I walked along handing out candy
canes.  I over heard a couple of children shout out very "excitedly".
Look they are giving away Jesus candy. And they wanted some.  I
thought about this later in the day.  It would be great if every one
thought of Jesus as candy.  Everybody likes candy!!  Most of the time
eating one piece of candy leaves you with wanting more.  Candy is good
anytime. Before a meal, after a meal, in the morning, in the
afternoon, in the evening or late at night.  I think those kids really
had something.  We need to tell everybody "Jesus is like candy".  Then
maybe every one would want some.

Philip
 

Saturday, December 2, 2006

     Eleven members of Baker Chapel worked at various times today. 
Dave Swann from the Dale UMC helped as well.  We installed all the
drywall on the ceiling in the utility room between the rest rooms.  We
started on the ceiling in the men's restroom.  Installed drywall on
the walls in the women's restroom.

Philip
 

Friday, December 1, 2006

     Volunteers included Baker Chapel members as well as, Gerald
Malott and Pastor Mel Mozingo from New Castle Christ's UMC.  They
installed drywall on the ceiling in the chase area behind the plumbing
wall for the restrooms.  They finished the walls in this area also. 
This was a very difficult area to work in because it is very narrow. 
They built the wall at the end of the shower in the women's restroom.

Philip
 

Thursday, November 30, 2006

     Six volunteers, all Baker Chapel members worked today.  They
finished installing drywall on the walls in the restroom next to the
nursery.  Yeah!  Check that room off the list.  They installed drywall
on the ceiling of the women's restroom.  They attached the plates to
the wall in one of the class rooms for second story storage.

Philip
 

Wednesday, November 29, 2006

     Volunteers installed the drywall on the ceiling of the
conference/library room.

Philip
 

Tuesday, November 28, 2006

     Frank's installed more duct work today, installed dampers and
parts to the fire alarm system.  The block layers returned today, and
worked on the south side.  Volunteers finished installing the drywall
on the ceiling in the nursery, and some on the walls in the restroom
next to the nursery.

Philip
 

Monday, November 27, 2006

     Today's volunteers were small in number.  But, they were large in
determination and a good heart.  They installed several corners and
starter strips for the vinyl siding.  Also another 100 sheets of
drywall was delivered today.  Some lumber was also delivered today. 
This lumber will be used for a bulk head in the sanctuary for lighting
and sound system.  We are also going to build some storage rooms
above a couple of the rooms.

Philip 
 

Saturday, November 25, 2006

     Fifteen volunteers worked at various times today.  Ron Devasher
from Avon UMC was back yesterday and today (for the second time). 
Mike Beaven from Newburgh and Tim Watson and his sons, from
Cloverdale.  The remaining volunteers were from Baker Chapel.  We
finished installing the drywall in the big hallway.  YEE HAW!!!!   I
know that some of you are wondering, how  big is this hallway, they
have been working on it forever.  Well it is quite big.  Many walls,
as well has many obstacles to work around.  We also finished the
closet next to the fellowship hall, the ceiling and the remaining
walls in the infant room, the ceiling in the restroom next to the
nursery, and started on the ceiling in the nursery.  We ran out of
drywall.  It is a good feeling to do the mental check-mark when a
room is finished.  Others worked on electric and installed caulking
around the duct work going through the outside walls.  Kristi Shreve
provided a hearty lunch of chili soup and grilled cheese sandwiches. 
We also polished off a few left over deserts in the frig.

Philip
 

Friday, November 24, 2006

      Volunteers worked under bright sunny skies today.  They finished
the soffit on the south side.  All of the soffit is finished now. 
They installed some flashing on the top of the cap stone.  This is in
preparation for the vinyl siding.  Others installed drywall on the
hallway walls, walls in the nursery and some of the ceiling in the
infant room.

Philip
 

Thursday, November 23, 2006

     HAPPY THANKSGIVING  !!!!!!

     Here at Baker Chapel we are thankful for all the people who have
given their time, talents and gifts.  Without these things that we
have received, the rebuilding of Baker Chapel would not be as
successful as it has been.  On this day of giving thanks, we give
thanks for everyone who has touched us with their love and support.

    Myself, I am thankful for my family.  I am also thankful for my
Baker Chapel family.  This family, from the "little ones" who let us
know they are in the church service to the members who come with the
support of a cane, wheel chair or some type of assistance and all of
the members in between.  Our Baker Chapel gives me love and warmth all
year.  I am also thankful for two very dear friends, who each brought their
combines and helped me finish my soybean harvest today.  What a joyful
feeling to complete harvest on the day we are to give thanks, for a
bountiful harvest.

     I hope you have many blessings to be thankful.

Philip
 

Wednesday, November 22, 2006

     Today, one block layer with two helpers worked.  These are paid
workers.  The block layers we had earlier were volunteers.  They were
unable to schedule anymore days.  We need to get the blocks finished
in order to start the vinyl siding.  They finished the capstone on
the north side.  Frank's installed more ductwork.  Others worked on
electric.  We are hoping to get some volunteers Friday and Saturday.

Philip
 

Tuesday, November 21, 2006

     Very few volunteers today.  They worked on electrical, clean-up,
and worked on sealing around the temporary doors.  Three block layers
worked today installing block on the south side of the building.

Philip
 

Monday, November 20, 2006

     It was reported in church yesterday that we received monetary
donations from Trinity UMC in Evansville and Huntingburg UMC.  The
Huntingburg UMC has also been providing meals for the volunteers every
other Monday.  We also received donations from some members of
Huntingburg in memory of loved ones.  Thank you very much.

     Today, Frank's installed more ductwork.  The two dry-wall
finishers worked.  Baker Chapel members covered the window sills with
plastic to protect them, finished putting weather proofing tape around
the windows on the outside, and worked on electrical connections.  Mr.
Lutz from Boonville also volunteered helping with the electric.

Philip
 

Saturday, November 18, 2006

     The work day today began with two volunteers.  Then their was
one.  Then  back to two.  By 11:00 a.m. a total of just seven
volunteers were working.  All the volunteers are members of Baker
Chapel.  I think that the fact that today was the first day of deer
season, resulted in a low turn out.  Today we finished installing dry
wall on the west wall of the sanctuary, finished the ceiling in the
big hallway, (Hooray!!!!!!!!)and installed some drywall on the walls in
the utility closet between the bathrooms.  Sid worked on electrical. 
Their was a crock pot of chili, sandwiches and cookies and fresh
coffee when we arrived this morning.  I think they were provided by
the Barnett's.  Thank you.  I found out today, that a friend of mine
from the Presbyterian church in Dale helped on the church yesterday. 
His help was appreciated.  The last two volunteers left a 4:30 p.m.
today.

Philip
 

Friday, November 17, 2006

   Today the work team of 5-women and 2-men from Noblesville First
UMC worked till noon.  They have been here all week and have
accomplished much.  The volunteer from Avon who was also here all week
was Ron DeVaisher.  His son Len, is a former pastor at Baker Chapel.
Ron's help was greatly appreciated.  Also today, six people from the
Conference worked.  Some from as far away as Corydon.  These
volunteers along with Baker Chapel members installed more dry-wall in
the hallway and on some of the walls.  They also constructed a
temporary front door, complete with hinges.  The electrician connected
wires to the breakers in the panels and worked on the electric supply
for the in-line water heaters.  Frank's installed more duct work.  It
was a partly sunny day with a cold breeze.  The last two days we have
received 2 inches of rain.  This weather pattern we have had since
August, of excessive rain, makes you wonder if we should be
constructing an Ark instead of a church.

Philip  
 

Thursday, November 16, 2006

     Volunteers today finished installing the rest of the fiberglass
insulation in the ceiling, finished installing the rest of the dry-
wall in the fellowship hall, and worked on dry-wall on the ceiling in the
big hallway.  The dry-wall in the fellowship hall has received one
coat of joint compound and some areas two coats.  The workers from
Noblesville started sanding some of the finished dry-wall joints.  The
electrician was on site today, not sure exactly what he got done.

Philip
 

Wednesday, November 15, 2006

    They delivered another 100 sheets of drywall today.  Two paid
professional drywall finishers arrived today.  It was decided that we
had too much drywall to finish for the volunteers.  They mainly will
be finishing the ceilings (install the tape and joint compound) and
high parts.  Knowing what to do and having the proper equipment really
makes a difference.  We still have a lot of drywall to install.  But
certain areas need to be taped and joint compound applied as soon as
possible on the ceilings.  It is easier to do before the duct-work is
installed in those areas.  More drywall was installed on the ceiling
of the fellowship hall.  The electrician was on site today and the
Ivy Tech crew was here also.  It rained most of the day.  If you
happen to live in an area that needs rain, I would suggest that you
start building a church. Ha! Ha!

Philip
 

Tuesday, November 14, 2006

     A total of 24 volunteers worked today.  They installed some
drywall on the ceiling of the fellowship hall.  Put more joint
compound on the drywall.  Moved all the tables, chairs, and
refrigerator into the kitchen for the lunch area.  They are all in
one room now, so everybody can fellowship while eating.  The
electrician worked today and Frank's installed duct work.  The block-
layers returned in full force.  The building gets seven rows of split-
face blocks and a 4" cap stone on the north, west, and south sides. 
The blocks are finished on the north side and west side.  They have a
good start on the south side.  They have done a few of the cap stones
as well.  I forgot to mention that they came and picked up the JLG
(large fork truck) last Saturday.  This is one of the rented pieces of
equipment we are using on site.   The rent on this machine was the
most expensive.  We are finished with it now and we are glad to see
it go.

On a personal note, I finished shelling corn tonight.  Praise the
Lord! They have forecasted heavy rain for tonight and tomorrow.

Philip
 

Monday, November 13, 2006

     Volunteers arrived today from Noblesville First UMC, Evansville
Presbyterian, Avon Methodist and Baker Chapel.  Also the block layers
returned today and installed several block.  Forty-five 5 gallon
buckets of joint compound was delivered today. Workers began putting
the tape and joint compound on the drywall screws and cracks. 

Philip
 

Sunday, November 13, 2006

     Today 19 members from Baker Chapel attended worship services at
St. Luke's UMC in Indianapolis.  They have 6000 members with 9000
people attending church.  They have three services.  They had asked
some to come for a program at each of the services.  Steve Barnett
spoke at the first service, Keith Shelton at the second service, and
Greg Perigo at the third service.  They then answered questions.  They
served a lunch to the Baker Chapel members as well as those that came
to Baker Chapel to volunteer from St. Luke's.  This is the group that
prepared and served the meals to all the people during the blitz week-
end in Sept.  Some of their members also came down to help with the
church.

Philip
 

Saturday, November 11, 2006

Happy Veteran's Day

     Four volunteers from Hew Hope UMC in Salem Indiana and one
volunteer from Highland UMC in Highland Indiana worked today.  Four
Baker Chapel members worked as well.  They installed drywall on the
walls in the infant room, nursery, and the bathroom next to the
nursery.  Sid worked on electrical.  It is unbelievable that they
drove 2 hours to get here worked till 3:30 p.m. then drove back home. 
These fine people like many before them leave with the same gracious
attitude.  When you thank them for coming to help us.  They all reply,
No, Thank You for letting us help.  Praise the Lord for all of the
good help that he sends to help us.  Cathey, and the Gentry girls
provided a nice hot pot of chili soup with deserts for lunch.  With
the cold front and dropping temperatures today, it was just right.

Philip
 

Friday, November 10, 2006

     Volunteers continued to install drywall today.  They did more of
the ceiling in the fellowship hall, bathroom walls and hallway walls. 
Frank's installed more duct work.  They installed more conduit leading
to the outside units.  The group from St. Luke's returned home today. 
They helped a great deal this week.  Thank you.

Philip
 

Thursday, November 9, 2006

     St. Luke's worker returned today.   They include 13 men and 2
ladies.  The ladies cook their breakfast and evening meals for them. 
They are from the East & West District.  Which extends from
Indianapolis down to Crawfordsville.  They even have one person from
Tennessee.  They installed drywall today in several areas.  They
finished the kitchen, started on the ceiling in the fellowship hall,
walls in the bathroom utility area, walls in the hallway, walls in the
pastor study.  They added some insulation in the inside wall of the
pastor study as a sound barrier.  Frank's added more duct work.  They
delivered another 160 sheets of drywall today.  I asked the truck
driver, and he thought each 4X12 sheet weighs 80 pounds.

Philip
 

Wednesday, November 8, 2006

     Volunteers installed drywall on the ceiling and walls in the big
hallway.  Frank's installed more duct work.  The electrician worked on
wiring.  The Ivy Tech class worked this morning installing conduit to
the outside heating and cooling units.

Philip
 

Tuesday, November 7, 2006

    First of all, I would like to clarify something.  I do not want to
get the credit for the web site.  The web site is designed and
maintained by Brad Buxton.  I only write the progress report, then
send to Brad.  He does whatever he needs to do, then posts it on the
web site.  Judy Shelton takes most of the pictures that are on the web
site.  Thank you to Brad and Judy.

Today volunteers continued to install drywall.  They finished the
ceiling in the kitchen.  Installed some on the kitchen walls, walls in
the conference room and some on the walls in the hallway.  Frank's
installed more duct work.  Their are three separate units for the
heating and cooling.  We will have three zones, one for each unit. 
This was determined to be the most economical way for conserving
energy.  Each zone will be separate, so we do not have to heat or cool
the whole building.  It appears that all the soffit on the north side
is complete.

I hope that you took the time to vote today!

Philip
 

Monday, November 6, 2006

     There is a very nice article in the paper today about our service
at Baker Chapel yesterday.  If you would like to read it, go to
www.courierpress.com/news/2006/nov/06/church-has-new-beginning/
If you would like to have more information about 'C.J.'s Bus' go to
www.cjsbus.org
Today several volunteers from Metro Ministries-St.Luke's worked at
Baker Chapel today.  They installed drywall on the ceiling in the
kitchen.  Some of them installed soffit on the outside.  They finished
the west side and worked on the north side.  Others installed more
fiberglass insulation in the ceiling.  The company came today and
installed the rubber roof to the top of the steeple base.  It is now
completely sealed.  The guy returned today to blow more insulation
onto the outside walls.  Frank's installed more duct work.  The
electrician worked on connections.  They delivered another 100 sheets
of drywall today.  It began to rain about 2:30 p.m.

On a more personal note.  I had a bad day.  This morning my cell phone
came off my belt while I was in the lift at church.  It fell 16 ft.
onto the concrete floor.  We found most of the pieces.  I found out
from the dealership today that my pick-up needs almost $800 in repairs
for brakes and ball joints. OUCH!  The feed auger slipped off the bin
roof and put 3500 pounds of feed on the ground.  Which I had to pick
up with a shovel.  It rained this afternoon (again).  Which means
their will be no harvesting of soybeans for a few days.  Today is the
one year anniversary of the tornado.  I am starting not to like
November 6 very well.

Philip
 

Sunday, November 5, 2006

     Webster's dictionary gives the definition for "celebrate" as:
1.  to perform, publicly, and formally 2.  to commemorate (an
anniversary) with ceremony or festivity 3.  to proclaim 4.  to honor
or praise publicly.
All of this definition's fit the description of what took place at
Baker Chapel today.  Today we held our first service in our new
building. Over 150 people gather today, just one day short of a year
of the tornado.  Our first song was " To God Be the Glory".  Tears of
joy streamed down my face during the entire song.  It was an awesome
feeling of love, and the presence of the holy spirit filled the
sanctuary.  Two firefighters from New York, one from Louisiana, and
one from Utica were also attending.  All of these men were here on the
Sept. 11 week-end when the rebuilding of Baker Chapel began.  Several
people (myself included) gave personal testimony of how the tornado and
the rebuilding has affected them. Words can not describe the
atmosphere.  Three different TV crews were in attendance as well.  At
one time during the service I noticed that one of the news people were
moved to tears, as were many others present.  Jeff Parness from the
New York Says Thank You Foundation also spoke to us.  He announced
that today at 2:00 a press conference would be held in Evansville. 
The purpose of this was to announce the start of a new foundation
titled CJ Foundation.  CJ is the name of a two year child you was
killed by the Nov. 6, 2005 tornado.  CJ was staying with his
grandparents in the mobile home park in Vanderburgh County.  CJ's
mother attended Baker Chapel today.  She felt something good needed to
come from the tragic death of her son.  The first thing this
Foundation plans to do is raise $100,000 needed to purchase, what will
be called CJ's Bus.  This bus will be a portable playground that will
go to different disaster areas, when disaster strikes.  It will be a
secure area operated by trained professionals, for parents affected by
the disaster to leave their children while they take care of immediate
needs.  This service was also the first time our new "Praise Team"
participated.  We also took part in communion.  It was very inspiring
to hear the testimony of many people.  Even though we sat on lawn
chairs, and had no heat.  The warmth from the love of people and the
holy spirit, was more affective than any heating system.

Philip
 

Saturday, November 4, 2006

     Twenty plus volunteers worked today.  The McCutchanville crew came
again today. Praise the Lord!  What a bunch of dedicated volunteers. 
They installed more drywall.  Baker Chapel crew installed all the
windows.  WOW!  Others helped with drywall and several did extra clean-
up. Several things were removed from the sanctuary in preparation for
service tomorrow morning at 9:00 a.m. They also installed some soffit
on the over-hang on the west side.

Philip
 

Friday, November 3, 2006

     The group from McCutchanville returned today.  We also had a man from
Newburgh helping as well as a few Baker Chapel people.  They
installed some drywall on the walls in the fellowship hall, sanctuary,
and kitchen.  They also installed some blocks between the studs in the
kitchen that will be used to fasten the cabinets to the walls. 
Frank's installed more duct work.  The electrician returned today.

Philip
 

Thursday, November 2, 2006

     Four volunteers from McCutchanville Methodist Church worked today as
well as about seven Baker Chapel members.  They finished installing
the insulation on the east wall.  Installed some drywall on the walls
of the fellowship hall and some on the west wall in the sanctuary. 
The heating guys installed more duct work.  The electrician was on
site today as well.  The company switched electrician's on us and the
one today spent most of the day familiarizing himself with the
project.  Which is not a good thing for us since we are paying him.

Philip
 

Wednesday, November 1, 2006

     It rained again most of the day.  The Ivy Tech electricians were back
this morning and again tonight.  They worked on wiring and installing
the fire alarm system.  Other workers today installed drywall to the
ceiling in one of the closets, and hallway.  They installed insulation
on the east outside wall.  They secured the showers in place.  They
installed more duct work for heating and air.

Philip
 

Tuesday, October 31, 2006

   Happy Halloween!!

     It rained most of the day today.  I failed to mention that the windows
were delivered yesterday.  I was unable to check the site last night. 
I was in the fields till 10:30 p.m. shelling corn.  So I
had not realized that they were delivered yesterday until this
morning. Sorry!   They block layers did not work today because of the
rain.  Two plumbers were back today.  They have finished the rough-
in.  They have capped everything and are doing the pressure testing. 
The two showers arrived today.  One will be in each of the restrooms. 
They are large, handicap accessible.  We have plans to add a gym onto
the building when funding becomes available.  Baker Chapel was, and
still is the designated Red Cross emergency shelter for Degonia
Springs.  These showers will be very useful if the building is ever
needed as a shelter.  Workers today installed drywall to the ceiling
of the sound room, and worked on the large hallway.  We hope to get
some of the windows installed this week.  We will be having service
this Sunday morning Nov. 5 in our new church.  Even though the church
is not finished, we decided it would be a great way to celebrate. 
We will be sitting on lawn chairs, and most likely wearing heavy
jackets.  But, we will be in our new sanctuary.

Philip 
 

Monday, October 30, 2006

     Five volunteer block layers arrived today.  They started laying the
split face block which goes around the church.  Two plumbers worked
today on water lines and making connections.  The heating and air guy
(Frank) installed more duct work.  It was a beautiful day today.

Philip
 

Sunday, October 29, 2006

     Kevin Green and Greg Perigo finished installing the vinyl siding on
the steeple base today.  Jennifer Green and Debbie Perigo put some
walk boards around the church.  This is so the block layers can get
around the church without walking through the mud.  Thanks guys and
gals.

Philip
 

Saturday, October 28, 2006

     Twenty-one volunteers worked today at different times.  Some working
in the morning, some in the afternoon.  And some worked all day
putting in almost 11 hours.  Mike and Tom Moesner from Dale UMC helped
today.  The rest of the workers were Baker Chapel members.  Derek,
Jacob, and Logan returned the remaining 10 picnic tables that we
borrowed from the 4-H center.  Five ladies did cleaning, sweeping and
picking up scrap, they also installed some insulation in the walls. 
We installed the drywall on the ceiling in two duct work closets, two
utility rooms, youth room, ministers study, office and some drywall on
the walls.  Installing the drywall on the ceiling is a very slow and
difficult job.  It must be two layers, to meet fire code. The ceilings
are 16 and 18 ft. off the ground.  The 4ft.X12ft. sheets are very
heavy.  We use a crank lift to raise it up to the electric lift.  Then
hoist the sheets to the ceiling. They installed some more siding on
the steeple base.  The Hoofers provided an excellent dinner.  It
consisted of roast, potatoes, carrots, corn, green beans, slaw and
rolls.  It was a feast, topped off with a desert that tasted like
heaven.  It was a good day today.

Philip
 

Friday, October 27, 2006

     The Noblesville crew worked a few hours this morning before heading
home.  We again, thank them for all their help this week.  I forgot to
mention yesterday they also worked on the lighting in the sanctuary. 
Today volunteers added more insulation.  We installed drywall on the
ceiling in two classrooms.  The company was here today to spray
insulation onto some more of the exterior walls.  The plumber was on
site today installing more pipes.  Others added braces to the wood
frame surrounding the duct work in the sanctuary.  It rained again
most of the day.  We have had over 2 inches of rain in the last two
days.

Philip
 

Thursday, October 26, 2006

     Well guess what?  It rained again, most of the day.  Volunteers worked
on installing drywall today.  They worked on walls and started on the
ceiling.  The fire code requires us to install two layers of drywall
on the ceilings.  Tonight a social time with deserts was attended by
several.  It was held at the Main Street Methodist Church in
Boonville.  It was a time for members to come and visit with the eight
volunteers from Noblesville.  They included 5 men and 3 women.  We
thank them for all their help this week.

Philip
 

Wednesday, October 25, 2006

     They have almost finished the insulation in the ceiling.  They
actually ran out of insulation.  They installed more soffit.  They
have installed the siding on the North side of the steeple base.  The
Ivy Tech group was back today and tonight.  They have installed more
lights in the sanctuary.  They were running more wires and making
connections.  The plumbers worked today, putting in pipes that  go in
the walls.  The sand was delivered for the block layers to use.

Philip
 

Tuesday, October 24, 2006

     The Mt. Vernon crew and Noblesville crew returned today.  They
completed more soffit on the eaves, and insulation in the ceiling.

Philip
 

Monday, October 23, 2006

     About 25 volunteers worked today.  Several were from First UMC Church
in Mt. Vernon Indiana.  Some were from First UMC Church in Noblesville
Indiana.  And a few of our own Baker Chapel.  The Mt. Vernon people
had called and said they would help with the insulation.  They have
well over half of the fiberglass insulation installed in the ceiling. 
Others worked on finishing the wood frame around the duct work in the
sanctuary.  Others started on the soffit (sp? trim around the eaves)
on the outside.  They got several pieces done.  More drywall was
delivered.  It was a good productive day.

Philip
 

Saturday, October 21, 2006

     Eleven different men who are all members of Baker Chapel worked at the
church today.  Some worked part of the day, some all day.  Our blessed
Jerol has been back working the last few days.  He was there early
this morning, and still working when I left at 5:00 p.m.  May God
truly bless his dedication.  Thank you Jerol.  Four ladies also worked
this afternoon doing a great job of sweeping and cleaning.  Don't tell
them that after they left, the floor got dirty again.  The Shelton's
provided a fantastic lunch of home-made chicken noodle soup, baked
ham, and fresh baked cookies.  Today we installed more drywall, almost
finished the wood frame around the duct work in the sanctuary,
installed insulation in the ceiling, and moved some electrical wires. 
Even though it was a beautiful day outside, we decided it was too
muddy to work on soffit.  Thanks to everyone who gave up their
Saturday to work on God's house.

Philip
 

Friday, October 20, 2006

     Very few volunteers today.  They installed more walk ways in the
attic.  Fastened boards on wall tops to attach drywall to.  Started
on the wooden frame, which will enclose the duct work in the sanctuary.

Philip
 

Thursday, October 19, 2006

     The Colorado team installed more drywall today.  As well as insulated
more duct work pieces.  They have installed some of the vents on the
under side of the roof edge, for ventilation.  They sealed some of the
bottom plates with caulking.  Today was the last work day for the
Colorado team.  This evening at Main Street Methodist church was a
social time with deserts.  It was an opportunity for Baker Chapel
members to meet these fine people and thank them for their help.

Philip
 

Wednesday, October 18, 2006

     Most of the drywall is installed on the sanctuary walls.  They did
stay away from the door and window openings so it would not receive
water damage.  Added more sound barrier insulation. They covered one
of the walls in the fellowship hall with drywall.  More duct material
arrived today.  The Colorado ladies covered several pieces with
insulation.  The Ivy Tech classes returned again today and worked on
electrical.  They installed the breaker panels inside the large
electric boxes and started connecting the wires.  Installed some of
the wires for telephone and sound system.  Kevin started on the soffit
under the eaves.  It rained again today.

Philip
 

Tuesday, October 17, 2006

     The Colorado team installed some insulation in the inside walls of the
sanctuary.  This is for a sound barrier.  They also installed several
sheets of drywall in the sanctuary.  Their are six men and four ladies
on this team.  They put some more walkway in the attic.  They are all
good hard workers.   More duct work was installed.

Philip 
 

Monday, October 16, 2006

     Ten volunteer "angels" came today from Mountain View Presbyterian
Church in Loveland Colorado.  They will be here all week.  They
started to install a walk-way in the attic.  They helped Frank's
Heating wrap insulation around the duct work, which they began to
install today.  Frank has graciously agreed to deduct from the price
of installation for the volunteers helping him.  It rained all day
today.  They also did some small electrical work today.

Philip
 

Saturday, October 14, 2006

         About 10 Baker Chapel members volunteered on site today.  They poured
the three pads of concrete for the HVAC units.  They also poured
concrete around the steel posts inside the building.  They worked on
electric.  They installed some drywall around the top of the side
walls in the sanctuary.  This is were the duct work will go, for the
heating and air.  They also cleaned-up some of the insulation "fuzz"
from the floors.

Philip
 

Thursday, October 12, 2006

     Today, some of the walls in the sanctuary received some blow-on
insulation.  They completely filled the 8 inch walls.  We are not sure
yet if we will do all the walls this way.  This was a quick way, and
good insulation.  We only did a few walls where the duct work will be
installed.  We will also drywall behind these areas before the duct
work goes up.  The other frame is completed for the third pad for the
HVAC units.  It appears that we might have some new members at Baker
Chapel for the choir.  On several nights well after dark (about 9:00
p.m.)you can here a couple coyotes howling.  They carry a nice tune.

Philip
 

Wednesday, October 11, 2006

     Today Frank's Heating arrived with sheet metal and duct work.  Frank's
received the bid to install the heating and air.  Ivy Tech students
returned today.  Bob Gourley trenched the line from the transformer to
the building.  They installed conduit and pulled the wires in from the
transformer.  Others finished the floor on the stage.  Lunch was
provided by Trinity Methodist in Rockport.  Supper was provided by the
Gentry girls.

Philip
 

Tuesday, October 10, 2006

     A few Baker Chapel members traveled to Bloomington today.  They picked up
 150 folding chairs that were donated by St.Paul UMC.  Don worked on
more forms for the pads for the HVAC units to sit on.  Others worked
on more wiring.

Philip
 

Monday, October 9, 2006

     A gentleman named Don, from Goshen Indiana arrived at Baker Chapel
today.  He will be here through Friday of this week helping.  He
worked on building frames for the concrete pad for the large heating
and cooling units today. Others worked on electric.  They also
installed some of the pipe in the mound system today, and added more
dirt.

Philip
 

Saturday, October 7, 2006

     There were a few volunteers that worked at Baker Chapel today.  This
week the number of volunteers have been smaller.   One of the reasons
is that some of the regular volunteers are farmers (like myself). 
Farmers are now busy working in the fields harvesting.  Today's
volunteers installed more tyvex (plastic) on the outside sheeting. 
They cut some of the access holes in the outside walls for the
heating/air duct work.  We hope to begin installing some of this next
week.

Philip
 

Thursday, October 5, 2006

     They stock piled more dirt for the mound system today.   Some clean-up
and picking up after last nights electrical crew.

Philip
 

Wednesday, October 4, 2006

     They added more dirt around the mound system today.  This morning 7
volunteers from Ivy Tech Community College worked on electrical. 
Tonight from 6-10 p.m. 15 from Ivy Tech worked on electrical.  They
pulled the large wires connecting the three panel boxes.  Installed
more conduit, pulled wires through some of the conduit.  Installed
electric wires between boxes.  These people are students who are
working towards their industrial maintenance certification.  The
building is large enough that they could all be working in different
areas at the same time.  I helped pulled nine wires through one of the
conduits this evening.  It really is pretty easy, when you have the
proper equipment and knowledge.  They will be back again next
Wednesday.

Philip 
 

Tuesday, October 3, 2006

     Some of the rock and sand for the septic system was delivered today. 
Bob Gourley Excavating began work on the mound system (septic) this
afternoon.  Bob and his family are faithful members of Baker Chapel. 
This donation of labor and equipment will be a huge savings to Baker
Chapel.  It has finally started to dry out.  Greg started leveling
some of the dirt off today, from where we got the clay to construct
the building pad.  Someone came today to look at the building to
provide a quote for the fire alarm system.

Philip
 

Monday, October 2, 2006

     Today's volunteer were small in numbers.  They installed more
Ty-vex (plastic) on the outside sheeting.  Worked on electrical wiring,
and did general clean-up.

Philip
 

Saturday, September 30, 2006

     Fourteen volunteers worked at different times today.  The outside
sheeting on the north wall is complete.  They installed the smoke
(fire-wall) board to the upper truss, on the two required areas.  They
did more electrical work.  Cut a groove in the concrete in the kitchen
floor for the electrical conduit going to the island in the middle of
the kitchen.  Worked on the stage flooring in the sanctuary.

Philip
 

Friday, September 29, 2006

     Today was the last day for the four people from Akron.  They consisted
of a husband and wife team and two other men.  They left about mid-
day for their 6 hour drive home.  They did great work this week, and
we look forward to them returning for our open house.  All of the
inside walls have now been framed except two short walls
next to the showers.  We will wait until the showers are picked out
before constructing these walls.  They installed more electrical wires
today and more lights in the sanctuary.  More small odd
jobs were completed as well.  Tonight Carl and I met with a guy about
using spray-on Icynene insulation.  He will provide us a quote in the
next few days.  We hope to have several here tomorrow for another good
work day.

Philip
 

Thursday, September 28, 2006

     The Akron volunteers returned again today.  These four people have
been very helpful this week.  They are all good workers and do very
precise work.  Some of the permanent lighting fixtures were
installed in the sanctuary.  Others helped with wire and conduit. 
They worked on shortening one of the inside walls.  It was to tall
and was getting to much pressure from the trusses.  It is not a
supporting wall but had too much weight on it.  Part of the day was
also spent making some small changes in headers, door widths, etc.  It
was quite hectic during the blitz week-end and a few things were
accidentally overlooked.  This evening, work began on the raised floor
in the sound room.  There is still a lot of work too be done, but
ever time a small project is completed we get a little closer. 
Leaving in the dark and looking back at the church, it is an awesome
silhouette in the bright lights.  I look forward to the day (night)
when we will see those famous candle lights, in the windows.

Philip
 

Wednesday, September 27, 2006

     Volunteers worked on the big inside wall again today.  The Akron
volunteers returned today.  They, along with others pulled more
electric wire.  Some students taking electrician classes at Ivy Tech
college were on site helping today as well.  Their was also a class
coming tonight from 6-10 p.m.  They mounted the big electric panel
today.  It is 42" wide and 7 feet long.  They began running the 2 inch
metal conduit.  They mounted one of the smaller panel boxes too.  All
the windows have been covered with plastic.  The top of the steeple
base was covered with plastic.  Their is a chance of rain again
tonight.

Philip
 

Tuesday, September 26, 2006

     Volunteers returned today to work on electric.  I failed to mention
yesterday that 4 of these volunteers are from Akron, Indiana.  They
are here helping as a mission trip.  One of the electric people is
Baker's own Sid Gerber.  We have an electric project manager who is
on site and being paid to help with and oversee the electric
installation.  Everyone else helping with the electric has been
volunteer.  The day shift volunteers today worked on building the
large inside wall by the fellowship hall.  They also installed the
second upper plate, to some inside walls, and installed more fire
blocks.  They placed clear plastic over some on the windows to keep
the rain out.  The evening shift volunteers worked on the steps going
around the stage.  Finished the hurricane clips. Praise the Lord! 
Installed some insulation in the walls, (behind the electric panel
board) and installed the fire proof board that the large electric
panel will get mounted to.  They also removed some bottom wall plates
in the doorways.

Philip
 

Monday, September 25, 2006

     The roofers returned today.  They installed the shingles on the small
roof in front and the ridge cap on the rest of the roof.  The roof is
complete. Yippee!!  Six volunteers started working on the electric
today.  They installed several boxes for switches and receptacles. 
Others worked on sheeting. Several left over materials that were not
needed were returned today.  This will be a credit to our account,
making the building material cost lower.

Philip
 

Saturday, September 23, 2006

     The work crew consisted of six people today.  All Baker Chapel
members.  That's OK, some of the other volunteers needed a break. 
They installed more fire-wall blocks and worked on constructing another
inside wall.  We are getting close to having all the inside walls
framed.  It seemed only fitting that after an evening of high winds,
tornado warnings, and lots of rain, that I installed some more
hurricane clips. While it poured down rain most of the morning.  For
those of you who don't know what a hurricane clip is,( I didn't know
either until this project) let me explain.  It consists of a twisted
metal bracket that connects the bottom of the truss to the top
plate.  You fasten this bracket with 10 nails, 5 easy nails and 5
difficult nails.  The difficult nails are driven through the metal
webbing that is on the truss.  I call these nails difficult because
in order to get them through the metal, you must first punch a hole. 
Actually, this is my process, which may not be the correct one but it
worked. (most of the time)  I have a black and blue finger nail for
the times it didn't work. Anyway, I thought I was done until we were
leaving and discovered I missed one corner.  Only seven more, I
decided to save those for another day.  OK enough about hurricane
clips.  We ended the day at 1:00. Most of us were tired of the rain
blowing in the window frames. We have had 5.1 inches of rain in the
last 48 hours.  Even though most of the shingles are installed.  A lot
of rain blew in the open areas for the doors and windows.  It is
always a risk when you mention names, for fear of missing someone. 
But I have to tell you that Carl and Jerol were back again today.  I
think that these two guys live there.  Their dedication for Baker
Chapel has continued from the old building to the new building.  These
two guys deserve to pick their seats in the new sanctuary.
Tonight was our ice cream social.  This is the annual fundraiser for
money for mission work.  Some of this money will still go to mission
work.  Just because, it always has.  For the first time, we held a
basket auction from donated items.  The basket auction money will go
to the building fund.

Philip
 

Friday, September 22, 2006

     Workers installed more sheeting on the outside wall, on the north
side.  They only had a small amount of time this morning before it
began to rain. They constructed a couple more inside walls.  We had
light rain off and on all day.  This evening it rained really hard with
lightning and tornado warnings.  As of 9:00 p.m. we have had 2.5
inches of rain today with more predicted tonight.  We had planned to
work tomorrow on the church.  Tomorrow night is our annual ice cream
social.  It will be held at the Warrick County 4-H center 4:30-7:00
p.m. with a basket auction at 6:30 p.m.

Philip

 

Thursday, September 21, 2006

     The roofers really went after things today.  They finished the
shingles on the big roof.  They still have to do the small roof over
the entrance and the ridge caps yet.  Volunteers put the outside
sheeting on the south side of the big gable end today.  A couple more
inside walls went up as well.  Some of the tops of the inside walls
were secured to the bottom of the trusses.  All of the metal temporary
bracing has been removed from the inside.  Everyday is a day closer,
but their is still a lot of work to do.  Guess what?  Chance of rain
the next couple of days. Bummer!!!

Philip
 

Wednesday, September 20, 2006

     The six roofers were back today.  My guess is that in the last two days
they have installed about 50 squares of roofing.  The roof has a total
of 162 squares.  More inside walls were constructed by local
volunteers and more of the wall braces have been removed.  We removed
two more of the large tents this evening that had been used to serve
meals under.

Philip
 

Tuesday, September 19, 2006

     Six paid roofers were on site today starting to install shingles. 
They completed the east section and have started on the large roof. 
They did get one of the motorized lifts stuck in the mud.  They were
able to pull it out with a cable.  The walls to one of the interior
closets and a couple small interior walls were constructed.  We began
installing the remainder of the hurricane clips on the trusses.  No I
am not crazy, I know we are not in a hurricane region.  This is not a
code requirement, however the building inspector requested that they
be installed. More sheeting was installed on the exterior walls.

Philip
 

Monday, September 18, 2006

     Rain all day today.  However, Pastor Rob Nelson who is a minister from
Goshen Indiana (this is at least a six hour drive) worked all day at
the site today.  He installed temporary lighting inside the
building.  Carl assisted him all day.  He just showed up this morning
and wanted to help.  He worked till after 5:00 p.m.  Rainfall today
exceeded 1 inch.

Philip
 

Sunday, September 17, 2006

     We had 15-20 volunteers work at the church this afternoon.  They
finished installing the rest of the tar paper on the roof.  This was
very important to help protect against the expected rain for tonight
and tomorrow.  I was unable to help today due to a prior commitment. 
They also installed some tyvex paper on the outside walls, this will
help with the rain protection as well.  They removed more of the
bracing on the inside.  Thanks to those who gave up their Sunday
afternoon to work on God's house.

Philip
 

Saturday, September 16, 2006

     A few volunteers arrived at 7:00 a.m. this morning.  About 20
different volunteers drifted in and out during the day.  The last one
leaving at 5:15 p.m.  Most were members of Baker Chapel, a couple were
good friends.  We added some more nails in the roof decking and
covered some of the area with tar paper.  That area covered with paper
is now ready for shingles.  They added the decking to the off set roof
around the steeple,  placed some more sheeting on the outside wall on
the north side,  did some general clean-up,  graded the parking area
and some of the mud around the building.  People continued to stop by
most of the day to check on the progress.  It is hard to believe that
only eight days ago the first board was placed on the building.  Grant
and Elena picked up nails with magnets. It was fun at first but it
quickly became boring.  They did a great job; every nail they found
did not find a tire. Some of the braces used to steady the walls have
been removed.  We ended the day by adding a 2X6 cross on top of the
church, fastened to what will be the base for the steeple.  I can tell
you, the view from the top of the steeple base is spectacular.  We
will continue to concentrate on installing sheeting and preparing the
roof for shingles.  With good weather we hope to begin installing
roofing next week.

Philip
 

Friday, September 15, 2006

     Twelve Mennonites returned today.  They finished setting all the big
trusses, as well as the tip top trusses.  They have all the decking on
the roof.  They installed the second section for the steeple.  They
worked on a couple more inside walls.  They have removed some of the
steel pipes, that were used for bracing.  There are two small 1/2
trusses not installed.  I am not sure if they are extra, or there
might have been a print change.   It is still unbelievable how much
has taken place in the last two days.  Those guys definitely know what
they are doing.

Philip
 

Thursday, September 14, 2006

     St. John Chapter 1 verse 51  "And he saith unto him.  Verily, verily,
I say unto you.  Hereafter, ye shall see heaven open, and the angels
of God ascending and descending upon the Son of man".

     The angels descended upon Baker Chapel today.  The angels came in the
form of 45-50 Amish and Mennonite workers.  I don't know exactly how
many, because they were moving so fast I could not count them.  It was
totally amazing. Their were also a few Baker Chapel people trying to
keep boards in front of them. They finished the trusses on the east
section that we had started last Sat.  That was seven more trusses. 
They installed all the decking and the tar paper on this section as
well.  They installed 33 of the big trusses on the west section.  They
placed 23 of the tip top trusses on top of those.  Most of these
trusses are already covered with the decking.  They constructed
several more inside walls.  At one point during the afternoon, they
were setting 6 trusses per hour.  Some of the workers were perched in
the trusses like birds.  When the next truss was set in place, they
would be ready to attack it with 2X4 bracing.  They have added some
framing for windows.  Started the upper walls for the steeple.
Several people provided lunch for the workers.  I am not sure how many
will return tomorrow.  They did not think they would all be back.  No
matter how many return, we will welcome them with open arms.

Philip
 

Wednesday, September 13, 2006

     The bad news is - "it has rained a lot".  The good news is - "it
rained this week, and not last week."  We have had 4 inches of rain in
the last three days.  It did look like someone might have swept the
water out of the church today, the concrete was dry.  It still amazes
me the amount of interest in the building.  The last two evenings
people who are not members came to the site while I was there.  Both
times it was drizzling rain.

Philip
 

Monday, September 11, 2006

     Work at the site was very limited today.  Greg Buxton fabricated some
metal hanger brackets.  These brackets were welded to the metal
support poles to hang the trusses on.  They were welded on by Greg
Buxton and Greg Perigo. Some more clean-up was done of loose debris. 
We had heavy rains today, with rain total in excess of 1 inch.  Their
is an 85% chance of rain tomorrow as well.  It might be a few days
before any progress can resume.

Philip
 

Sunday, September 10, 2006

     Volunteers arrived this morning at 6:30 a.m. to set-up chairs for the
memorial service.  They cleaned the bleachers and picked-up things. 
The memorial service was quite impressive.  The bag pipes, color guard
parade of fire fighters, and first responders will not soon be
forgotten.  The choir from Centenary U.M.C. provided the music.  After
the service which included Communion everyone stood in front of the
new building for a group picture. I tried to count those in
attendance.  I estimate that between 650-700 people attended.  I am
quite certain that this is the largest number of people to have ever
been on this holy ground at one time.  This may have been the first
time for this large number of people, but I don't believe it will
be the last.  After the group picture the Gentry sisters sang "God
Bless the U.S.A". Which grew a large applause.  Everyone was invited
to a delicious brunch served by St. Luke's Methodist Church of
Indianapolis.  I am sure that I have left many things out which took
took place these last three days.  It was truly an awesome experience,
of which I will never forget.

Philip  
 

Saturday, September 9, 2006

      Some workers began arriving at 6:30 a.m. this morning to begin
working.  Today more inside walls were raised.  The outside wall
sheeting that is installed is completely nailed.  Some of the vapor
barrier was installed on the sheeting as well.  We set the BIG support
truss which is the dividing truss close to the center on the church. 
After this truss was drilled and bolted into place, eleven matching
trusses were placed next in line.  Most of the required firewall
spacer blocks have been installed as well.  Several new volunteers
were helping today as well as a large number of spectators.  The
Mennonites were not available today due to a prior commitment.  The
Warrick County Red Cross were on site both days providing excellent
care.  Many times throughout both days, businesses sent out treats and
refreshments.  We thank you.  Special thanks to Greg and Debbie Perigo,
Jerol and Bonnie Watson, George, Cindy and Elizabeth Lewis for their
added dedication.  They stayed late to help move bleachers and items
preparing for the service tomorrow.  Tomorrow at 9:00 a.m. will be a
memorial service on site.  It is suggested to arrive early because the
highway will be closed during the procession of firefighters and first
responders.  A large crowd attended the community BBQ at Boonville
High School.  The firefighters played past members of the BHS girls
softball team in a slow pitch softball game.  These last two days an
amazing amount of work has been done, but we still have a long
way to go.  Thanks to ALL the volunteers up to this point.

Philip
 

Friday, September 8, 2006

     Their were two TV stations already on site at 6:15 a.m. this morning. 
Activities began at 8:00 at Main Street Methodist Church in
Boonville.  It began with a breakfast, followed by several speakers
and presentations.  The Mennonites who were here to help today left
the breakfast at about 8:45 a.m. They were very eager to begin
rebuilding.  Immediately upon arriving on site and after a safety
meeting, they quickly went to work.  At about 10:00 the other
volunteers who attended the full program began arriving.  At 10:15
I placed a bible in what will be our new sanctuary.  This bible was in
the former church and survived the tornado.  This bible remained their
all day.  At 11:00 the first section of wall was erected.  It was on
the west wall in the north corner.  Tears of joy streamed down my
cheeks when I realized that they had used my chain from my truck to
support this wall while lifting with the fork truck.  This was the
biggest section to go up at one time all day.  Most sections were
supported by the lift in the center while a line of volunteers lifted
as well.
11:35 - Middle section of west wall.
12:00 - South section of west wall.
12:25 - Middle section of south wall.
1:45 - South wall east end corner.
2:20 -East wall south corner.
2:25 - North wall west corner.
2:35 - East wall 2nd. section.
2:50 - North wall 3rd. section.
2:55 - North wall 4th. section.
3:05 - East wall 3rd. section.
3:00 - 3:15 North wall sections. 4 and 5
3:15 - North wall section 6.
3:30 - North wall last section
SHAZAM !!!!!  All outside walls were up.  As you can tell by the
times which are fairly accurate. More than one crew was working in
different locations.
3:40 - The inside wall of the entrance area went up. (This is
actually considered on outside wall).
5:20 - The first interior wall went up next to the kitchen.
Most of the exterior OSB board has been installed.  The raised stage
area in front of the sanctuary was built. The second interior was 
raised.  The third wall is built and ready to be raised.
The trusses are on site.  I am unable to give you a report for the
events after 7:00 p.m.  I left to attend the BHS football game were
my son Logan was recognized with 17 other students, who received a 4.0
during the spring semester. (proud dad) 
I can not put into words the feeling that comes from working on this
new building.  Many will return to the site tomorrow to continue the
building. Breakfast, lunch on site, and an evening meal on site was
provided and prepared by St. Luke's United Methodist Church in
Indianapolis, Indiana.  Thank You.

Philip
 

Thursday, September 7, 2006

     Neil's crew finished the concrete this morning.  The four vertical
steel support beams in the middle have been installed.  The lumber is
now on site in several piles.  Tonight two more tents went up.  At
5:00 p.m. news 14 was on site.  At 8:00 p.m. Fox 7 news was on site. 
Tomorrow is the big day when all the New York firefighters as well as
many other volunteers will arrive.  Skelton Township fire dept. hosed
down the old parking lot tonight.  Tomorrow we will Rock-N-Roll.  I
forgot to mention yesterday that a new flag pole was installed.
 

Philip
 


Wednesday, September 6, 2006

     Concrete workers were on site early this morning.  They have poured
2/3 of the slab, about 110 yards of concrete.  The plumbers finished
this morning. Yippee, Yeah, Hooray!! (it is about time)  After the
plumbing was inspected, Neil's crew quickly went to work.  They added
the rest of the rock, plastic, and this section is now ready for
concrete which they will pour tomorrow.  Several more loads of rock
were added to the parking area. Vectren buried the line to the
transformer for electricity. Beginning at 4:30 p.m. a host of several
volunteers went to work.  Some of these workers continued past 9:00
p.m. tonight.  They moved two tents, set-up four huge tents and got
another tent ready to go up.  Brought in 7 more sets of bleachers and
thirteen more picnic tables.  Put up signs and probably things I don't
even know about.  It was amazing.  Preacher Mike's sermon last Sunday
was titled "I will Dance! I will sing".  I can tell you tonight under
the glow of the two huge parking lights and the moon, that slab of
concrete was beautiful.  We're going to have an awesome place
to "Dance and Sing". 

Philip
 

Tuesday, September 5,2006

     Neil Barnett and his crew installed the rock, which goes under the
concrete slab.  They plan to pour concrete on 2/3 of the slab
tomorrow.  The plumbers were on site today.   They should finish in
the morning.. Then the plumbing has to be inspected. The plumbers have
been the hold-up.  That is why they can only pour 2/3 of the slab. 
The remaining part is where the plumbing is located.  They hauled
rock and added to the entrance and some in the north parking lot. 
The only had one truck available to haul rock today.

Philip
 

Monday, September 4, 2006

     While many people celebrated Labor Day as a day off.  Work on Baker
Chapel continued today.  Brad and Greg Buxton along with Kevin Green  finished the
conduit for the sound system.  Greg and I moved dirt most of the
afternoon.  We have finished the final grade for the remainder of the
North parking lot and the new entrance.  It is now ready for rock. 
Debbie Perigo cleaned mud from the parking lot (right before we added
more) sorry Debbie.  Mike Watson mowed and Mary Beth removed sprouts
from the bank along the highway.  This evening several people helped
to move two bleachers and 20 picnic tables to the site for next week-
end.  Thanks, to Scott, George, Logan and Philip for trucks and
trailers.  Also thanks to all the people who helped load and unload. 
We  finished in the dark tonight.  I realized that we will be needing
two generating power plants for additional lighting.  Can anyone help
with this?  The next few days will be very busy. Please pray for safe
and speedy progress.

Philip
 

Sunday September 3, 2006

     Work at the building site was very limited today.  We needed a break. 
Kevin Green worked on installing conduit for the sound system in the
sanctuary.  This will be under the concrete floor.  This was actually
a re-work.  The sound person changed their mind from yesterday as
what size it needed to be.  It needed to be larger.  Some of us worked
on the lay-out on were to position tents, bleachers, etc. for next
week-end.

Philip
 

Saturday, September 2, 2006

     WOW !!!!!!!!!!!!!!!!  What a difference a day can make.  Today was a
big progress day at Baker Chapel.  Workers began today at 7:00 a.m. 
We began in a drizzle type rain.  It sprinkled heavy at times, but
everyone kept on working.  Several volunteers were on hand today. 
Some staying all day, while others worked while they could.  I called a
couple of my good friends last night for help today.  Special thanks
to Dale Downey from Schnur Farms for mowing the parking and tent
area.  A big thank you to Kurt Stahl of Stahl farms.  Kurt brought a
big tractor with dirt pan.  He moved dirt for a few hours, and left
his machine for us to use the remainder of the day.  The repairs to
the other dirt pan from our breakdown yesterday  made it through the
day. (Thanks to Bobby Gourley for a good welding job)  At one time
today I counted 27 cars in the parking lot,  belonging to all the
workers.  Some lovely ladies provided lunch and the coconut cream pie
was like a slice of heaven.

     A lot of clean-up work was done today, both on site and next door.  I
lost track, but I think we had at least 12 truck loads of rock
delivered.  All but 2 loads were used in the parking lot area and
driveway.  The other 2 loads were used as back-fill around the
concrete blocks.  Before adding the back fill rock, a termite control
barrier was sprayed and the perimeter tile was installed.  Some of
the floor area has been covered in plastic.  The entire floor area
must be covered with rock before the concrete is poured.  We moved a
lot of dirt today.  Most of it was for controlled drainage  and
bringing the rest of the parking area up to grade.  The last of the
workers left at 6:50 p.m. to the start of a beautiful sunset.  The
only time I think the sun shined all day.

Philip
 

Friday, September 1, 2006

     It was a good day at the building site today.  I am afraid to try and
mention names of workers today, in case I leave some one out.  I can
tell you that at 4:00 their was still 7 men on the job.  All members
of Baker Chapel. They finished the block today.  They poured the
concrete for the electric transformer.  They installed the Styrofoam
inside the blocks. We have put three truck loads of rock on the North
parking lot.  I can tell you that, three loads does not go very far. 
We have cut the entrance to grade and have placed one load of rock in
the entrance.  We have three trucks scheduled to haul rock until noon
tomorrow.  The plumbers got a good start on the plumbing today.  We
hope to have several on hand to help tomorrow with various tasks. 
Their is still a lot of interest in the construction.  From 6:30 p.m.
till 8:00 p.m. this evening six vehicles entered the parking lot to
check out the progress.  We might want to consider start charging a
spectator fee for the building fund.  I am sorry I do not know who
served the workers dinner today.  I did not help with the site until
4:00 today and they were still talking about the great tasting
casserole.  One of the wheels broke off the dirt pan this evening. 
Hopefully our repair job will hold, we will give it a good test
tomorrow.  Please continue to pray for the safety and speedy progress
of our workers.

Philip 
 

Thursday, August 31, 2006

     The block layers arrived early this morning.  They had a good day, I
would say that 3/4 of the block are now done.  Neil Barnett began
digging for the plumbing, which goes under the concrete slab. Kevin
Green, Jerol Watson, and Carl Barnett have the area ready for
concrete, that the transformer sits on.  I know someone brought lunch
today.  I do not know who (sorry about that)but thank you very much.
If others helped that I did not know about, thank you as well. We hope
to have several help Sat.  We have several small jobs that need to be
completed.

Philip
 

Wednesday, August 30, 2006

     Today they did some block preparation work.  The did not actually lay
any block.   They moved some block and mortar to the building site. 
They also spaced block out getting ready.  They hope to start actual
laying of block tomorrow.  It is still to muddy to do anymore dirt
work.

Philip
 

Tuesday, August 29,2006

   Today volunteers removed the mud, dirt, and cleaned the concrete
footings.  Those that I know of who worked are Gene and Carol Green,
Greg Buxton, Judy Shelton and Carl Barnett. Thank you very much.  I
have been told they look great. If any others helped, thank you as
well.  Kevin Green dug the trench and footing for the concrete pad for
the transformer.  I myself did not work on the site today.  It is
possible they might start laying block tomorrow.

Philip
 

 

Monday, August 28,2006

   The concrete blocks and mortar was delivered today as scheduled. 
Because of the excess rain and mud, the blocks were placed on the old
parking lot.  When the ground dries, they will return to place the
blocks at the building area.  It is hopeful that with no more rain,
they could be able to lay the blocks on Wed. Because of the ground
conditions, no other work was performed today.  We are once again,
reminded that, we are on God's schedule.

Philip
 


 

Sunday, August 27, 2006

   Well, Greg and I had big plans today.  We were going to get the north
parking lot to final grade, so it would be ready for rock.  We
intended to work more on the drainage water-way.  We intended to get
the field across the road mowed, to use for parking. The Rudolph Bros.
and Bob and Ruth Peters are going to let us use the field across from
the church as parking for cars during the week-end of Sept. 8. God had
different plans for us and the site today. At about 1:30 p.m. (shortly
after we began) it began to rain.  This ended work on the site for
today.

Philip
 


 

August 26, 2006

   Workers were on site at 6:00 a.m. today.  They finished the re-bar,
and the first concrete truck arrived at 7:00 a.m.  I failed to mention
yesterday that we have only prepared the footings for the church
building.  We have NOT done the gym footings, until we can get a
better idea of funding.  The concrete was poured today in the church
building footing.  Several people were on hand to help.  We were
blessed today with no rain at the site.  Greg and I continued to move
dirt today.  When we left the site today at 4:45 p.m. it still had not
rained on site.  It had rained very hard less than 1/2 mile away at
about 2:30.   We really owe Greg Perigo a huge thank you.  His
expertise in blue prints and moving dirt has saved several thousand
dollars.   Lunch was again served, to those still working at noon. 
Thank you to Dorothy, Gayle and Marsha, it was a welcome treat. 
Tomorrow's work schedule will depend on the weather.  The concrete
blocks will arrive on Monday, as will the block layers, weather
permitting.

If we have as much interest in Baker Chapel after it is built, as we
have had during construction, it will be great.  It is almost a
constant flow of on-lookers.

Philip
 



 

August 25, 2006

WOW!!!!!!

  What a day at the building site.  Today, Ash Iron Springs
Construction, Gourley Construction, and Green Construction began
digging the footings today.  We had several additional volunteers, who
came a different times today.  And by 6:30 p.m. today most of the re-
bar had been installed and secured.  Tomorrow morning at 7:00 a.m. the
concrete trucks will start arriving.  Also today, Greg Perigo
installed the culvert to the entrance over the waterway.  We will test
this entrance tomorrow with the concrete trucks.  We received a nice
lunch and a wonderful blackberry cobbler.  Thanks to Jeff and Noel
Loehr, and Carol Green.  Pray for no rain.

Philip
 

 

August 24, 2006

Greetings,

  This is the first of what I hope to be many current updates on the
building project for the web site.

Today we finished final grading of the dirt pad for the building. The
final compaction test was taken and approved. This evening Doug Bacon
and Kevin Green measured, and marked the perimeter out for the
footing. I continued to move dirt for the surrounding area.

Tomorrow morning, they will begin digging for the footing. After the
footing is dug out, re-bar will be added and secured in the footing.
The next step would be to add the concrete to the footing.

Philip