|

Join Us
Sunday
Services being held at
Baker Chapel
Worship 9:00 am
Fellowship 10:15 am
Life Groups 10:30 am
Quick Links

|
|

|
|
|
|
|
|
Daily
Progress Report
Wednesday, August 29, 2007
Tonight nine of us that are going on the Texas trip next week met
at the church for a conference call. Sept. 6-9,
ten Baker Chapel members and four other members
of the Boonville community will travel to
Groesbeck Texas. They along with many other
volunteers from around the country will join the
New York Says Thank You Foundation build their
2007 project. We will build a new house for
James and Eva Vincent and their family. Their
house was destroyed by a tornado last December.
For more information about the family and the
foundation, visit their website
newyorksaysthankyou.org
Participating in the conference call were the
following:
Baker Chapel
Jeff - New York Says Thank You Foundation
Co-founder and organizer of the build projects.
Starvos - New York Says Thank You Foundation
Co-founder and General contractor.
Bob - Lead Builder on this project.
Brian - Pre-construction Services Manager for a
construction company in Dallas Texas.
Charlie - He was the Construction Supervisor in
charge of the Twin Tower clean-up in New York.
Those of us at Baker Chapel spent one hour
finalizing our travel plans and preparing
questions for the conference call. The purpose
of the conference call was to get everybody
updated on the project. We were able to
establish a projected time-line for the
different areas of construction. The house
consists of 2700 square feet with a covered
porch and an additional garage. They will pour
the concrete tomorrow morning. We intend to
arrive in Texas on Sept. 6 in the early
afternoon. We will evaluate the sight and help
prepare the lay out. The work days will be Sept.
7-8. We hope to have the house completely
framed, siding installed, decked and a
possibility of roofing as well in these two
days. If it is God's will, his plan and his
time-line, we beleive it is possible. We at
Baker Chapel are very excited about having this
opportunity, to give something back by "paying
forward".
Philip
|
Monday, August 27, 2007
Tuesday, August 28, 2007
Volunteers worked today grading, seeding grass and covering with
straw. They also started watering the seeded
areas today. It has been very hot and dry here.
I think the temperature has been above 91
degrees for the last 24 days. They decided that
we needed to get the grass starting to grow. It
needs to get some growth on it before this fall.
Philip
|
Sunday, August 26, 2007
DEDICATION SUNDAY!
Open House was held from 1:00 to 5:30 p.m. With the dedication
service beginning at 5:30 p.m. Six different
singing groups entertained in the sanctuary all
afternoon. They included; New Harmony Voices,
Mt. Gilead Singers, First Baptist Church,
Lighthouse Praise Team, The Holders, and the
Baker Chapel Praise Team. The opening song for
the Dedication Service was "I'll Fly Away". This
was the first song that was in the bulletin
November 6, 2005, the day the tornado hit. We
recognized four former pastors who were in
attendance today. Their was a time of
reflection. A few people spoke about a specific
experience with Baker Chapel. Most of them were
about the tornado or since that time. District
Superintendent Rev. Glenn Howell shared words
and performed the Consecration of the Building.
The closing song led by the Gentry Sisters and
the Baker Chapel Praise Team was "We are
Standing on Holy Ground". The scripture for the
service was Psalm Chapter 84: 1-4, 10-12 and
Matthew Chapter 7: 24-27. Over 600 people signed
the registration book through out the day. And I
am quite certain that many people missed the
book. We also severed BBQ pork, hamburgers, hot
dogs, drinks, cake and many varieties of
homemade cookies. It was a blessed day to thank
the many volunteers, and to give God all the
Glory, for what he has done.
Philip
|
Saturday, August 25, 2007
Volunteer members finished food preparation today. Others worked
outside grading the parking lot, mowing,
trimming, and picking up materials to allow more
parking. They prepared the programs, and did
last minute cleaning, and installed pictures on
some walls.
Philip
|
Friday, August 24, 2007
Volunteers worked at the church today preparing food. They are
making potato salad, slaw, veggie trays, bake
beans, and a host of other things for the
Dedication this Sunday. Others worked on
cleaning.
Philip
|
Thursday, August 23, 2007
I arrived on site this morning at 5:05 a.m. Neil and his concrete
crew and Kevin were already working with lights.
The concrete pumper truck was setting up, and
the laser screed was being prepared. The first
load of concrete began unloading at 5:35 a.m.
The last full concrete truck was unloaded at
7:58 a.m. The remaining concrete needed was
measured and called in for delivery. By approx
8:45 a.m. with a little help from a few
volunteers the last of the concrete was poured
for a total of 72 yards. By 2:00 p.m. the
concrete had been troweled, grooves cut and
sealer applied. The concrete had coloring
installed. I don't know the "official" color.
But I will describe it as a "light colored
chocolate". They finished none too soon, as
temperatures reached 100 degrees this afternoon.
Other volunteers removed forms from yesterdays
concrete and seeded grass on the former building
site.
Philip
|
Wednesday, August 22, 2007
Neil and his concrete crew returned today. His crew along with
other volunteers, set the J-bolts in concrete to
attach the side-wall plates. They also
constructed and poured the concrete pads that
the pillars will be installed on, for the
drive-thru canopy. They installed the rock base,
and prepared the area for the concrete floor.
Tonight, several volunteers worked on cleaning
the inside of the church. We also installed
several signs, posters, and did things in
preparation for the open house on Sunday August
26.
Philip
|
Tuesday, August 21, 2007
Volunteers finished placing the back fill (with rock) around the
foundation. This evening, Spike put some more
top soil onto the old building site, in
preparation for seeding.
Philip
|
Monday, August 20, 2007
Volunteers returned today. They installed the perimeter drain tile,
around the foundation of the Life Center/gym.
They covered the tile with rock. They also
installed the insulation on the inside next to
the block, and back-filled with rock. They
removed the bottom four feet of siding on the
east side of the church. Eventually all of the
siding on the east side will be removed. It will
be reinstalled on the sides of the Life Center.
They removed the bottom four feet only, so it
did not get any concrete on it, when the floor
is poured.
Philip
|
Thursday, August 16, 2007
Six block layers arrived today. They installed two rows of 12 inch
block, and one row of 8 inch blocks. They have
completed all the block work for now. The
remaining split-face block can not be installed
until the walls are constructed. Volunteers
installed more erosion control blankets in the
drainage area. They also seeded more grass seed,
and strawed the area.
Philip
|
Wednesday, August 15, 2007
The concrete blocks, sand and cement was delivered today for the
multi-purpose building. Greg finished removing
the rest of the old asphalt this evening. Spike,
Kevin, and Derek worked on hauling and leveling
dirt on the old building site. They also
installed some rip-rap around the large culvert
under the entrance. The Praise team practiced
tonight for their part in the Dedication
Celebration. The decorating committee met
tonight making plans. Today was also the 18th
day in a row for temperatures over 90 degrees.
The actual temperature reached 104 degrees
today. This was the hottest day since back in
1966.
Philip
|
Tuesday, August 14, 2007
Volunteers poured concrete pads in front of the doors on the south
and west sides of the church today. They also
sowed more grass seed, and covered it with
straw. We worked on removing some of the old
asphalt this evening.
Philip
|
Monday, August 13, 2007
Neal and his concrete crew arrived today. They along with other
volunteers, had a very big, progressive day.
They dug the footings, installed the re-bar and
poured the concrete. These are the footings for
the multi-purpose building. They also did the
same thing for the four columns, that will
support the overhead drive-thru. Once this is
completed, you will be able to drive a car under
the canopy to load and unload in inclement
weather. It was very hot today, but we stuck
with it, until the task was completed. I also
delivered several bales of straw, that they used
to cover the seeded areas.
Philip
|
Wednesday, June 20, 2007
I went to the church early today before going to work. I moved
some dirt from the top soil pile to where we
took up the old parking
lot. I did this for two reasons. The dirt pan we
are using belongs
to the Warrick County Soil and Water District.
They have been letting
us use the dirt pan free of charge. They rent it
out for people to
use. Someone wanted to rent it, and they were
coming to pick it up
today. The other reason is; I needed little one
on one "God Time". I
will be giving the message next Sunday June 24,
I needed to clear my
thoughts.
Philip
|
Saturday, June 16, 2007
I finished hauling away the rest of the busted asphalt today. I
was also able to separate two loads of rock that
was under the old
parking lot. I dumped it in the corner of the
new parking lot. We
can use this for base at a later day. I also
loaded three wagon loads
of straw behind the baler for us to use for
landscaping.
Philip
|
Friday, June 15, 2007
I started hauling away the busted up asphalt from the parking lot
this evening.
Philip
|
Wednesday, June 6, 2007
Greg finished busting up the remainder of the old parking lot on
the west side. He also graded some more dirt
around the drainage
ditch.
Philip
|
Monday, June 4, 2007
Greg worked on leveling more dirt around the drainage ditch. He
also put some top soil around this area for
seeding.
Philip
|
Saturday, June 9, 2007
Greg and Derek worked a couple hours this morning moving top
soil, working on the drainage ditch, and they
started tearing up the
asphalt in the old parking lot on the west. We
have not had any
measurable rain for about three weeks, it is
very dry.
Philip
|
Thursday, June 7, 2007
They delivered the pipes for in the ground for the gutter
downspouts today. Sunburst Stained Glass company
of Newburgh
installed the stained glass above the front door
today. They donated
the glass and labor. It measures 72" X 72", and
is just beautiful.
Greg moved more dirt this evening.
Philip
|
Wednesday, June 6, 2007
The Operators Union delivered a small dozer today, for us to
use. Greg started this evening using the dozer
to grade and level the
drainage ditch. Volunteers worked some this week
moving in and
cleaning more items.
Philip
|
Sunday, May 27, 2007
AWESOME!!!!!
Today was the first official service in God's new church. The
praise team started practice at 8:00 this
morning, and people began
arriving for church at 8:05. Church starts at
9:00. When we held our
service at other places, most of the time people
would start arriving
only 20 minutes before service. I sat in the
hallway before the
service, and just listened to the people has
they came in the
building. Some of the comments I over heard
were; "We should just
dance", "Just Amazing", "Wonderful", "It's so
beautiful". Their were
a lot of new faces, and some we haven't seen for
awhile. Their were
158 who celebrated in God's house today at Baker
Chapel. We began the
service with the congregation singing; 'I'll Fly
Away'. This was
supposed to be the first song on the morning of
the tornado. It was a
very tearful and moving experience for many,
myself included. Most of
the message included comments from several
members, as well as some
guests. Most talked about their experience
during the rebuilding, or
shared what Baker Chapel means to them. Prior to
singing our closing
song, 'Standing on the Promises'. The Gentry
trio sang God Bess
America. The Holy Spirit was truly among us
today.
Philip
|
Saturday, May 26, 2007
First of all, I want to apologize for not giving daily updates
this week. I have been working 16&17 hours a day
trying to get the
crops out and hay baled. I even missed praise
team practice this
week. I was going back over some of the updates
the other night and
realized that I had left out two very important
things. We received a
$2500 donation from the children in a Jewish Day
School in New York
City last month. This was money that they
themselves raised. They
want us to use this money to buy supplies for
our Sunday School. I
also failed to mention that starting last Easter
morning, people began
writing scripture on the concrete floors. Some
people signed their
name with the scripture, some did not. I wish
that I had took the
time to write down each of the different
scriptures that people had
written. It was really neat, to see different
ones show up almost
everyday. I made a couple phone calls last night
to find out what
took place this week. Now for this week's
progress report.
Our dishwasher and ice machine was delivered on
Wednesday. Thursday
night about seven people met in the evening for
training on how to
operate the sound system. On Friday the sound
system was completed.
A new couch and two new chairs were also
delivered on Friday. They
will be in the hallway. We will be having our
first service in the
completed church tomorrow May 27, 2007. It is
not really a secret,
but we wanted to keep a low profile on our first
service. It had been
announced at church the last two Sunday's.
Members who were not in
church received an e-mail or letter. The media
has been very good to
us, but we wanted our first service too be just
us. It is not really
a secret anymore. Their was an article on the
front page of the
Evansville Courier today, telling about our
first service tomorrow. I
am really excited, and I expect this "special"
first service, to be
the first of many.
Philip
|
Friday, May 18, 2007
Some more new tables arrived today. Our new piano for the
sanctuary was also delivered. We are leasing
with the option to
purchase. We are going to try this piano and if
we do not like it,
they will bring us another style. Volunteers did
more cleaning.
Philip
|
Thursday, May 17, 2007
The county building inspector came today. He inspected the
entire facility. He discovered a few small
things that he would like
changed. However, he did approve that it was
ready for occupancy.
Volunteers cleaned several folding chairs, and
started wiping the
dusty walls.
Philip
|
Wednesday, May 16, 2007
The last two doors were delivered today. Volunteers installed
these doors, and all of the remaining hardware,
on all the doors. The
carpet installers returned today and finished
all the carpet trim, for
the baseboard. Volunteers also cleaned more
dishes.
Philip
|
Monday, May 14, 2007
Tuesday, May 15, 2007
The company came and installed the wire mesh safety glass in the
inside doors that have windows. The four
entrance doors into the
sanctuary, have a window in the shape of a
cross. The carpet
installers have installed the 4 inch carpet
boarder on the walls in
the sanctuary, and the fellowship hall. They
also installed the
mud/tracker carpet in the foyer entrance. I am
not sure if that is
exactly what it is called, but it is supposed to
keep dirt from being
tracked in the building. Volunteers worked Tues.
evening cleaning out
the utility room, and cleaning up. Some of the
items were put in the
storage trailer, and some items upstairs in the
attic storage. They
worked on several small things, that needed
finished.
Philip
|
Saturday, May 12, 2007
Today, God showed me that his plans, and his schedule were
different than what I had planned. You see I had
planned to work
ground most of the night last night, and try to
finish planting corn
today. Then travel to Purdue University where my
daughter will
graduate tomorrow. Well it rained yesterday. So
instead of being in
the fields, I got to help 20 plus other
volunteers move pews into the
church. These pews were donated to us last year
from First Christian
Church in Newburgh Indiana. We had them stored
in a building at the
Spencer County fairgrounds. With four trailers
we were able to move
them all in one trip except for two pews. Sid
and Marsha spent many
hours cleaning the upholstery and the wood work.
I think they look
great. I think their are 22 pews, and they fill
the sanctuary. They
should seat a little over 200 people. Other
volunteers finished
installing door closure's, finished installing
the hardware and braces
on the restroom stalls, paper holders and other
small jobs. I still
left for Purdue, I just had the pleasure of
helping move the pews
before leaving. They also cleaned, and brought a
few more things into
the building. We still need to finish some
things, and have the
building inspector return. I can just say, that
everyday is a day
closer to completion.
Philip
|
Friday, May 11, 2007
I forgot to mention that the sound guy came yesterday, and he
brought more of the sound system. He worked on
securing the ends on
several of the sound cables. Only one carpet
installer worked today.
He finished the steps on the stage in the
sanctuary. He also cut all
the strips for the base board. We are using
carpet as a base board in
every area where their is carpet. He will take
these strips back to
the carpet shop, to have the top edge sewed.
Volunteers cleaned more
dishes, and placed them in the kitchen cabinets.
The lock smith came
and installed all of the lock cylinders on the
doors with locks. Greg
and Kevin worked on installing panic bars on the
required doors this
evening. It rained this afternoon.
Philip
|
Thursday, May 10, 2007
Only two carpet installers worked today. They installed the
carpet on the stage, the sound room, and the
reading platform in one
of the classrooms. Volunteers installed the
remaining door closure's
that we have on hand. Two of the closure's are
on back order.
Philip
|
Wednesday, May 9, 2007
The carpet installers finished the carpet on the sanctuary main
floor. Their is a 16 inch boarder around the
sanctuary with a
different color carpet. This was very time
consuming. Volunteers
installed two more door closure's this evening.
Philip
|
Tuesday, May 8, 2007
The carpet installers returned today. They started installing
the carpet in the sanctuary. They completed over
1/2 of the floor.
Ten new round tables were delivered today for
the fellowship hall.
Volunteers installed two more door closure's
tonight.
Philip
|
Monday, May 7, 2007
Volunteers cleaned dishes and some folding
chairs today. A few
of the dishes were salvaged from the tornado.
Some of the dishes were
donated by another church. Volunteers also
installed door handles
today. Kevin and Greg worked tonight installing
door closure's and
panic bars. They were still working at 10:00
p.m.
Philip
|
Saturday, May 5, 2007
At least 11 volunteers worked at different times today. There
might have been more, but that was the count
when I left at 1:00. We
finished installing the rest of the doors on
hand. We have two more
doors, that we rejected due to shipping damage.
We installed several
of the door handles and some closure's. They
cleaned the cabinets in
the kitchen, as well as the refrigerator, and
floors. They also
cleaned-up in several other areas. They also
moved everything out of
the sound room, in preparation for the carpet.
Philip
|
Friday, May 4, 2007
The carpet installers finished the classroom, library/conference
room, small hallway, utility closet, the room
behind the stage wall,
and rolled out some of the carpet for the
sanctuary. The rest of the
carpet was delivered today. Volunteers installed
the video screen and
some of the automatic door closure's.
Philip
|
Thursday, May 3, 2007
The carpet installers returned today. They finished the
fellowship hall, youth room, utility closet, and
started on one of
the classrooms. I was returning home tonight
from a track meet and
stopped by the church. It was after 8 p.m. and
Greg and Kevin were
installing some more doors.
Philip
|
Wednesday, May 2, 2007
They finished installing the carpet in the big hallway, and
started on the fellowship hall today. Tonight I
was rained out of
the fields. I helped Greg and Spike install 6
doors. The remaining
hardware for the restroom partitions was
delivered today. Everyday is
a day closer to being completed.
Philip
|
Tuesday, May 1, 2007
Our new freezer was delivered today. The carpet installers
returned today. They installed carpet in one of
the classrooms, coat
closet, nursery, infant room, and started on the
big hallway.
Philip
|
Monday, April 30, 2007
Five big rolls of carpet was delivered today. The carpet
installers also started today. They installed
the carpet in the
office, and the minister's office. They also
installed the carpet pad
on the stage, and the stage steps. Volunteers
installed door handles
on the doors that they installed Sat. They put
more items into the
storage trailer. We decided instead of just
moving things from one
room to another, to stay out of the way of the
carpet. We would just
move things one time into the trailer. Some of
these items will stay
in the trailer for quite some time.
Philip
|
Sunday, April 29, 2007
Jerol, Bonnie, and I, worked at the church tonight. Bonnie and
Jerol finished vacuuming the sanctuary and the
stage. I repaired and
replaced the three access holes that we cut in
the stage floor to
install the speaker wires. I also loaded the
scaffolding in my truck,
so it can be returned tomorrow.
Philip
|
Saturday, April28, 2007
A few volunteers worked today. They installed six of the inside
doors. These doors were in the areas with the
tile floor. Others
removed several items from the church and placed
them into the storage
trailer. The carpet is scheduled to be delivered
on Monday.
Philip
|
Friday, April 27, 2007
The interior doors were delivered today. We have 30 inside
doors. We rejected two of them because they were
damaged. There was
no school today. It was a scheduled 'snow
make-up day'. Since school
was never closed due to snow, the kids got the
day off. Some of them
helped to unload and carry in the doors. Five of
us worked tonight.
We cleaned the saw dust out of all the cabinets,
swept and vacuumed
most of the floors, picked up debris. We did not
get finished, but
we did get tired. We stopped at 10:00 p.m.
Philip
|
Thursday, April 26, 2007
The plumbers returned today. They finished installing all of the
sinks except two. Installed all the in-line
water heaters. They have
the water turned on and everything checked. They
will have to return
when the other two sinks arrive, as well as some
of the faucet
handles. Volunteers finished the final
electrical connections to the
grinder pumps for the septic system. They also
installed the two
microwaves under the cabinets in the kitchen.
Philip
|
Wednesday, April 25, 2007
The plumbers returned today. They repaired the pipe in the wall,
that the cabinet maker drilled into. They
installed the sinks in the
men's restroom, one of the double sinks in the
kitchen, and the under
the counter water heaters. Volunteers worked on
electrical
connections and applying polyurethane.
Philip
|
Tuesday, April 24, 2007
Volunteers worked on applying polyurethane to the window trim.
They also picked up the left over blocks around
the building. The
tile workers returned today. They finished all
the tile, they had
left out for the cabinets. They applied the
grout around the showers,
and finished the remaining base boards. The tile
is now complete.
Greg and Kevin started installing the counter
tops, they completed the
tops in the infant room, nursery restroom, youth
room, and several
pieces in the kitchen. They secured the counter
tops any place that
their will be a sink.
Philip
|
Monday, April 23, 2007
Greg and Kevin started installing the partitions in the men's
restroom this evening.
Philip
|
Sunday, April 22, 2007
Joyce and Jennifer presented their final landscape design for
Baker Chapel today. They arrived before service
to display their
poster designs and answer questions, for anyone
who could not stay for
the presentation after church. They have
designed and divided the
landscaping in three phases. The idea of three
phases allows us to
proceed as the funds become available. They did
a great job on both
the design and their presentation. They will
both graduate in May
from Purdue University with a degree in
Landscape & Horticultural
Design. They were given the task of designing
the landscaping for
Baker Chapel, as their senior project. I hope
that they get an A+.
These are two very fine young ladies, who really
cared about their
project. Two of their family members came with
them today as well.
Jennifer's mother Sharon, and Joyce's sister
Jennifer. After their
presentation, we went to Baker Chapel, so they
could see the progress
since they last visited. I also learned that
they will be
participating in the same graduation ceremony as
my daughter Maggie.
How great is that! I will get to see all three
of them receive their
diploma's.
Philip
|
Friday, April 20, 2007
The counter tops for the kitchen cabinets, youth room, and
restroom sinks were delivered today.
Philip
|
Thursday, April 19, 2007
Carol and Gene applied polyurethane today. Sid finished the
receptacles in the kitchen. I helped Sid and
Carl finish installing
the chandelier light in the foyer. Greg, Kevin
and I worked tonight
in the women's restroom. We finished the
partitions, installed on the
stall doors, latches, and coat hooks. This was
quite a task. We were
determined to keep going until we had the
women's side complete. We
worked until 10:25 p.m. We will still have some
work to do in the
restroom, but the stalls are complete.
Philip
|
Wednesday, April 18, 2007
Volunteers worked today applying polyurethane and cleaning up.
Sid installed the receptacles for the stoves in
the kitchen. He also
started installing some receptacles in the
island of cabinets in the
center of the kitchen. The microwaves and range
hoods were picked up
today. Greg, Kevin, and I worked tonight
installing the partitions in
the women's restroom.
Philip
|
Tuesday, April 17, 2007
Greg, Kevin, and Spike worked tonight. They installed the trim
around the top of the stage floor. They also
started to layout the
materials for the partitions in the restrooms.
Philip
|
Saturday, April 14, 2007
Several of us helped with a BBQ fundraiser today. The proceeds
will help with the expenses of the youth mission
trip to Colorado this
summer. For the last few years the Baker Chapel
Youth group and the
Main Street UMC Youth group have been doing a
combined mission trip.
They also do a lot of other activities together.
Yesterday they
cooked 24 pork butts. Last night we pulled and
BBQ them and placed
them in 1 pound containers. Today we grilled 48
slabs of ribs, and
over 100 chicken halves. We were sold out by a
little after 12:00.
It rained most of the morning. Since we helped
with the BBQ and
started at 6:00 a.m. this morning, no one worked
at the church today.
Philip
|
Friday, April 13, 2007
The cabinet maker returned today. He finished installing the
base cabinets in the kitchen, youth room,
nursery, and nursery
restroom. He also installed more wall cabinets
in the youth room and
the nursery. He accidentally drilled a hole in
the water line behind
the wall in the women's restroom. They came and
measured for all the
counter tops today. Two new cooking stoves and
one new refrigerator
were delivered today.
Philip
|
Thursday, April 12, 2007
The cabinet maker returned today with more cabinets. He started
installing the base cabinets in the kitchen. The
partitions for the
restroom stalls were delivered today. The
hanging light for the foyer
was picked up today. Volunteers worked applying
polyurethane on the
completed windows. Greg started on the trim,
that goes around the top
of the stage.
Philip
|
Wednesday, April 11, 2007
Two volunteers worked today applying the final coat of
polyurethane on the two windows in the foyer.
Seven volunteers worked
this evening. We helped the sound guy install
and secure the large
speakers above the stage. He also worked on
hooking up some of the
different units used in the sound system. Some
of the ladies on the
decorating committee met at the church tonight
to pick out the cabinet
counter top. Four of us then worked on
installing the trim on the
window in the fellowship hall and the youth
room. All of the windows
have been trimmed. We finished the last window
at 9:15 p.m. We would
have finished sooner, but we had to perform
surgery on the nail gun.
Philip
|
Tuesday, April 10, 2007
Volunteers installed the conduit and electric wire from the
building to the septic pump. Others worked on
applying polyurethane
to trim on the finished windows. Some more of
the sound equipment was
delivered today. I did not realize that the
cabinet maker also
installed the wall cabinets in the youth room
yesterday.
Philip
|
Monday, April 9, 2007
Two plumbers were on site today. They installed all of the
toilets and mounted the two water coolers on the
wall in the hallway.
The cabinet maker delivered and installed, all
of the wall cabinets in
the kitchen. Volunteers applied polyurethane to
the completed
windows. Bob installed a trench for the electric
from the building to
the sewage pumps. He also leveled some of the
dirt on the south side
of the building. Kevin, Greg, Spike, and I
worked tonight. We
installed the trim around the window in the
nursery, and both windows
in the foyer. Spike installed some of the
weather strips around the
double doors on the east side. Several people
have written scripture
on the concrete floors. We announced in church a
couple weeks ago,
that anyone could write their favorite scripture
on the floor, before
the carpet is installed.
Philip
|
Saturday, April 7, 2007
Bonnie and Debbie applied the second coat of grout sealer today.
Greg and I worked on trim this afternoon. We
completed the trim on
the second window in the minister's office, the
window in the office,
and the window in the infant room. We also
removed the protective
masking tape from the windows that are
completely finished.
Philip
|
Friday, April 6, 2007
Six volunteers worked today. All Baker Chapel members. They
finished installing the pipe from the septic
tanks to the mound
system. They finished some electrical
connections and installed
receptacle covers. They filled the nail holes,
and applied the final
coat of polyurethane on two window frames.
Frank's reinstalled the
large vents that Carl painted. The company came
and picked up the
electric lift today. This was the last piece of
rental equipment. It
seems that I have an admirer who is a critic.
Today I received my
second anonymous letter in the mail. First of
all, I hope that as you
check the website daily for my grammar mistakes,
that you are also
learning about Baker Chapel. Secondly, since you
do not think enough
of yourself to supply a return address, I am
responding to you with
this website. In my defense, I would like to say
that most of the
time I do the progress report late at night,
after working at least 12
hours or more, and attending one of many
meetings in many volunteer
organizations in which, I am involved. Yes, I do
make mistakes. I am
not perfect. Finally, I would like to point out
that the letter you
sent on March 13; my name was misspelled and you
had the wrong zip
code. In the letter you sent today; some of your
corrections are
wrong. However, I do want to thank you for
helping me with my
grammar. I only wish that you could correct me
before I place in on
the website.
Philip
|
Thursday, April 5, 2007
Bob worked on the water leak again today. He has repaired the
leak, and we now have a valve and water inside
the building. He also
started installing the line from the septic
tanks to the mound
system. Others worked on electrical connections,
and applying
polyurethane to some trim.
Philip
|
Wednesday, April 4, 2007
First of all, I wanted to give you a little more information
about the ladies from Terre Haute that have been
helping this week.
Jeanne is a member of Emmanuel UMC and worked
Monday. Pam and Kathy
are both members of Barbour Ave. UMC and worked
Monday, Tuesday and
part of today. We hope they are blessed by
blessing us with their
help. Today volunteers finished removing the
high spots in the
expansion joints. Carol worked on the trim that
has been installed.
She used steel wool to get a smooth surface, and
filled the nail holes
in preparation for the final coat of
polyurethane. They stained the
custom made receptacle covers for the window
receptacles for the
candle lights. This covers were made by Jerry
Lutz. They also
stained the last cross for the windows. Bob
Gourley started working
on repairing the water line outside that
developed a leak during the
freezing weather. When we installed the outside
hydrant last fall, we
made the mistake of securing it with a steel
post. When the ground
froze in January, the loose dirt raised up with
the water line and the
post would not allow the hydrant to move.
Therefore it placed things
in a bind and the pipe cracked. Kevin and I
worked on trim tonight.
He had already completed the window in the
classroom by himself before
I arrived. We also got one of the windows
finished in the ministers
office.
Philip
|
Tuesday, April 3, 2007
Two ladies returned to volunteer today from Terre Haute. They
helped clean the tile in the kitchen, men's and
women's restroom, and
the restroom in the nursery. They also helped
with clean-up. Other
volunteers helped to finish removing the high
spots in the expansion
joints and install a light in men's restroom.
They delivered the
remaining exit signs today, and they installed
them as well. Tonight
Bonnie and I sealed the tile grout in the
kitchen, men's and women's
restroom and the restroom in the nursery. Greg
and Kevin worked
tonight and 'trimmed-out' the other two windows
in the sanctuary.
Philip
|
Monday, April 2, 2007
Three ladies from Terra Haute, Indiana volunteered at Baker
Chapel today. They cleaned, swept, and vacuumed
several rooms. Carol
and Gene applied polyurethane to the trim
pieces. Other volunteers
did some touch-up painting and installed the
three drop ceiling lights
in the sanctuary. Tonight Greg P. and Kevin G.
started installing the
trim. They trimmed out two windows in the
sanctuary, the door-way to
the coat closet, around the open area window in
the sound room, and
around the opening were the projector screen
will be installed. The
trim looks great. It really sets off the
windows, and the cross at
the top gives it a special touch.
Philip
|
Saturday, March 31, 2007
The grills were fired up at 4:30 a.m. this morning. I arrived at
5:00 to help put the meat on. Jerol, Greg, Kevin
and I helped at
various times with the BBQ fundraiser today. As
I had mentioned
yesterday the money will go towards a new roof
for South Friendship
GB church in Boonville. We cooked 96 slabs of
ribs, 300 pork chops,
and almost 500 1/2 chickens. They served pork
chop dinners, 1/2
chicken dinners, and pulled pork dinners. You
could purchase single
chops, chickens, or pork butts. We used almost
50 gallons of BBQ
sauce. Some of the Baker Chapel ladies donated
deserts. We had 12
big cookers and four small cookers. They had a
lot of volunteers
help, and the deserts, baked beans and potatoe
salad was all donated.
I had BBQ ribs for supper tonight and it was
delicious. I worked at
home this afternoon. I worked at the church
tonight applying the
final coat of polyurethane to several pieces of
trim. When I left at
9:00 p.m. it was beginning to rain. We were
supposed to have
scattered showers most of the day. God blessed
us by holding the rain
away from the BBQ. I don't think anyone else
worked at the church
today. But I forgot to mention that Carol and
Judy worked on trim
yesterday. I began the day serving God by
helping another church. I
thought it was only proper to end the day
serving God at Baker Chapel.
Philip
|
Friday, March 30, 2007
The tile workers applied the grout in the tile in the foyer.
They installed some tile border around the
showers in the restrooms.
They put grout in the tile border in the
restrooms as well. Jerol,
Carl and Harley volunteered today helping to
cook 98 pork butts for a
fundraiser tomorrow. Tennyson General Baptist
and Mt. Gilead General
Baptist are hosting a fundraiser tomorrow for
South Friendship General
Baptist Church in Boonville. The proceeds will
go towards a new roof
for their church. These same two church's held a
similar fundraiser
for Baker Chapel last year. In southern Indiana
we really don't pay
attention to different denominations among
churches. If another
church needs help and we can do something to
help others, we just do
it.
Philip
|
Thursday, March 29, 2007
Tile workers worked in the foyer again today. They also did a
small area inside the second set of doors.
Volunteers worked today
doing touch-up painting and working on trim. Six
of us worked tonight
sanding, sealing, and applying polyurethane to
some of the trim. Some
of the trim has all the needed coats. All of the
trim has at least
been stained. Everyday is a day closer to
completion.
Philip
|
Wednesday, March 28, 2007
The tile workers applied the grout between the tiles in the men's
and women's restroom. They also cemented some of
the tile down in the
foyer. The tile in the foyer is 12 in. X 12 in.
and the tile in the
other areas is 16 in. X 16 in. The tile in the
foyer is very time
consuming. Their will be two crosses inlaid into
the tile floor.
This requires a lot of extra angles and extra
cutting.
Philip
|
Tuesday, March 27, 2007
The rest of the trim was delivered today. More sound system
supplies were delivered today. Volunteers have
attached some of the
finished trim to the stage. The tile workers
finished the tile in the
men's restroom, and did more layout work for the
tile in the foyer
entrance.
Philip
|
Monday, March 26, 2007
Four tile installers worked yesterday (Sunday) and finished
installing the tile in the kitchen. They worked
again today. They
applied the grout between the tiles in the
kitchen. They installed
most of the baseline, boarder tile in the men's
and women's restroom.
They started cutting the tile for the foyer in
the entrance of the
church. Volunteers worked applying polyurethane
to the trim today.
This evening Greg, Kevin and Spike worked on
trim. The rest of the
trim was delivered today. Their is a triangle
piece of trim with a
cross attached that will go at the point of each
of the windows.
Philip
|
Saturday, March 24, 2007
While most people were enjoying the beautiful 80 degree spring
day doing something for themselves. Nine
volunteers enjoyed the day
serving God at Baker Chapel. Under the direction
of expert gutter
installer Jimmy Volz and his helper Zach
Collins, along with Baker
Chapel members, they installed the remaining
gutters and all the down
spouts today. They also applied polyurethane to
several window
casings. They sanded some of the trim in
preparation for the second
coat of polyurethane. Two paid tile installers,
finished the women's
restroom floor, and started on the kitchen
floor. These guys are true
craftsmen. Anybody who can take six floor tile
and cut them into 36
pieces to craft them in a design around the
floor drain, is in my
opinion "a craftsmen". We ending the day around
3:30, with the
pleasure of having served God.
Philip
|
Friday, March 23, 2007
The correct number of volunteers from Epworth UMC in Indianapolis
is four men, and three women. They have been a
big help the last two
days. They worked till 3:30 p.m. today before
returning to
Indianapolis. They put the ceiling tiles back in
the kitchen, stained
the rest of the trim work, applied sanding
sealer to all the trim,
and started applying polyurethane to the trim.
They finished
constructing the reading platform in one of the
classrooms. They
installed more sound system wiring and cable.
The gutter crew
installed the one piece, seamless gutter on the
west side of the
building. They were then rained out, and had to
quit.
Philip
|
Thursday, March 22, 2007
Today, Baker Chapel welcomed at least eight volunteers from
Epworth UMC of Indianapolis Indiana. They along
with some Baker
Chapel member volunteers, did a lot of work
today. They installed the
outside lights by the front door, installed
speaker cable and wire,
installed several speakers for the sound system
in various rooms,
stained several pieces of trim, applied sanding
sealer to a few window
casings, and constructed a reading platform in
one of the class
rooms. They also installed a work counter (large
shelf) in the sound
room. Wow, that was a long list. Four people
installed floor tile.
They finished the floor in the men's restroom,
and started on the tile
base board. They have the women's restroom floor
3/4 completed. The
tile company owner came and removed the tile in
the kitchen. Then the
people who did not install the tile properly,
came and removed all the
tile cement, by grinding and sanding. The
materials for the gutters
were delivered today, and placed in the
construction trailer.
Philip
|
Wednesday, March 21, 2007
Greg stained some of the trim to be used around the windows
today. Kevin and Greg Greene worked several
hours. They installed
the door handle hardware on two outside doors,
closures on three
doors, and thresholds on two doors. They also
started on the hardware
on the east-side double doors. Carl has spray
painted two of the
large grills for the return air, in the heating
system. A crew of
four worked this evening till 9 p.m. installing
tile. This crew knows
what they are doing. They installed more tile in
the men's restroom,
and have started on the women's restroom. Last
night Kevin and Spike
removed all the ceiling tiles in the kitchen.
When the floor tiles
are removed for replacement, they will have to
grind the tile cement
off the floor. This will create a lot of dust.
They removed the
ceiling tile, so they will not get dirty. More
sound system supplies
were delivered today.
Philip
|
Tuesday, March 20, 2007
Greg stained the last two window casings today. He also applied
sanding sealer to the four windows he stained
yesterday. Sid
installed the boxes in the floor stage, for the
sound system. A new
tile installation crew (three people) arrived at
4:30 p.m. today.
They started in the men's restroom. The decision
has been made, to
remove the floor tiles in the kitchen. They will
have to grind the
tile cement off the concrete floor, clean and
install new tiles. The
tile company will pay for this re-work and the
new tiles.
Philip
|
Monday, March 19, 2007
Greg stained four window casings today. The wire and cable was
delivered for the sound system. Greg and Kevin
met with the company
salesperson this morning,that we are getting the
floor tile and carpet
from. We are not satisfied with the workmanship
of the tile
installation. The purchase agreement included
installation.
Therefore we are paying to have the tile and
carpet installed. We
told them we wanted the tile installation to
stop until this issue can
be resolved. The tile is not being installed
properly.
Philip
|
Friday, March 16, 2007
Three paid floor tile installers returned today. They installed
the tile in the laundry room and have installed
almost all of the
kitchen floor. They are cementing the tile to
the concrete floor.
After all the tile is installed they will put
the grout in the grooves
between the tiles.
Philip
|
Thursday, March 15, 2007
Jerol painted the finish coat of paint in the closet next to the
youth room. He installed the receptacle covers
in the youth room.
Bonnie also helped. Three people started
installing the floor tile
today. They installed the tile in the restroom
next to the nursery.
They also did about 1/3 of the kitchen floor.
Philip
|
Wednesday, March 14, 2007
Jerol painted the finish coat of paint in the youth room today.
Two people started on the tile layout on the
floor in the kitchen.
Philip
|
Tuesday, March 13, 2007
Jerol and Bonnie worked at the church today. They finished
taping the rest of the windows for staining.
Installed insulation
around the remaining windows and the attic door.
They swept the
floors were the tile will go. They painted the
final coat of paint on
the west steel door.
Philip
|
March 12, 2007
Greg and Jerol were the only volunteers today. They put the
second and third coat of paint on the double
doors on the east side.
Two coats of paint on the steel outside door on
the west side. They
did some touch-up painting around the air vent
grills. Frank's came
today and installed the permanent thermostats
and picked-up all their
ladders. The boards for the trim were delivered
today. The tile,
grout, glue and supplies for the floors were
delivered today.
Philip
|
Saturday, March 10, 2007
Five volunteers worked this afternoon, all Baker Chapel members.
We did several different things. We added some
braces in the steeple
base, finished the attic access doors, painted
the second coat of
paint on two outside doors, applied the first
coat of paint on the
(double) steel outside doors on the east side,
attached the handles on
two exit doors, and one threshold on one outside
door. It was another
beautiful spring day.
Philip
|
Friday, March 9, 2007
Today was a beautiful sunny spring day. Temperatures reached 72
degrees. The frogs were singing, the wild
turkeys scraping for bugs,
and the geese seemed confused as to which
direction they should fly.
A man from the fire alarm company was on site
today, installing the
alarm box and making wire connections. A few
volunteers from Newburgh
were back again today. They began scraping the
caulking that was
placed in the expansion joints. After it has
dried, the caulking
needs to be scraped, so it is smooth with the
floor. They also
stained two more window casings today. Someone
mentioned to me last
week that it looked like we were about done with
the church.
Although, everyday is a day closer their is
still a lot of things to
do. The volunteers from Newburgh this week have
been a big help.
Even though some of the things might have seemed
small. They did
several things, and their help was a big step to
being closer to
completion. We thank them, and may God Bless
them, as they have
blessed us.
Philip
|
Thursday, March 8, 2007
Volunteers from Newburgh and Baker Chapel continued working on
touch- up painting today. They also stained four
more window casings,
and painted two of the outside steel doors. They
installed the
fire/smoke alarm handles, that arrived
yesterday. They sealed more
expansion joints in the concrete floor.
Philip
|
Wednesday, March 7, 2007
Six volunteers from Newburgh UMC returned today. They continued
to seal the expansion joints until the ran out
of caulking. They
finished sanding and taping off the rest of the
windows. They are now
ready for staining. Frank's had a company come
today to check and
adjust the air flow to all the vents today. They
had previously
installed damper controls in the duct-work so
they could change the
flow if they needed too.
Philip
|
Tuesday, March 6, 2007
Several volunteers from both Newburgh UMC and Baker Chapel
worked today. They worked on sealing the
expansion joints in the
concrete with foam and caulking. Sanding the
window casings, and
stained two windows casings. They did touch
paint in several areas.
They also installed some electric wire. Frank's
heating installed the
remaining grills over the heat and air returns.
Philip
|
Monday, March 5, 2007
Six volunteers from Newburgh UMC worked at the church today.
They applied another coat of paint to the men's
restroom. They
repaired some small damaged areas to the drywall
in several rooms.
They also sanded the window casings in
preparation for staining. They
finished installing the insulation around the
window edges, and
installed several receptacle covers. They were
assisted by two Baker
Chapel volunteers.
Philip
|
Saturday, March 3, 2007
Jerol was the only volunteer who worked today. He applied the
final coat of paint in the library. I think he
was still a little
jittery (sp?) Sunday morning. I think he drank
the whole pot of coffee
by himself. Jerol still remains a very dedicated
angel volunteer to
this project.
Philip
|
Friday, March 2, 2007
Volunteers finished installing the rest of the steel door
frames. They worked on connections for the
fire/smoke alarms. They
hooked up the lights in the sound room. Most of
the ceiling tiles
have been installed. A few have been left out to
have access for
electrical connections and duct-work
adjustments.
Philip
|
Thursday, March 1, 2007
Six volunteers worked today. We traced down a missed electrical
connection. The receptacles were not working in
the library. Sanded
the library walls in preparation for another
coat of paint. They also
installed some of the emergency lights. Greg G.
installed several
steel door frames. The telephone guy came to
check into running the
underground wire back to the church. Heavy rain
and winds this
afternoon.
Philip
|
Wednesday, February 28, 2007
Volunteers installed the track lighting above the stage, and
hooked up the lights. They installed safety
wires to the remaining
lights, and installed some of the emergency exit
lights. Carl
finished painting the remaining door frames
today. He said he painted
25 frames, with each frame having three pieces.
Mid-west picked up
their lift and scaffolding today.
Philip
|
Tuesday, February 27, 2007
Volunteers installed ceiling tile in the restrooms, closet and
kitchen. They also continued work on the fire/
smoke alarm system,
and making electrical connections. The restroom
lights are complete.
Carl painted more door frames.
Philip
|
Monday, February 26, 2007
Mike with Mid-west finished his work today. Volunteers finished
installing ceiling tiles in the hallway,
nursery, office and
minister's office. They also worked on
installing the fire/smoke
alarm system. Carl took more door frames home to
spray paint.
Philip
|
Sunday, February 25, 2007
"With God ALL things are possible"
Matthew Chapter 19 verse 26
The building committee announced today that this spring when the
weather permits. We will be moving forward, with
the construction on
the multi-purpose building. This building will
be attached to the
east side of the church. It will be over 6000
square feet. Include a
multipurpose area the size of a Jr. High gym.
large youth room and
large storage room. It will also have a covered
area in front for
unloading/loading in bad weather. This was on
the original plans, but
we wanted to make sure we had funds available.
We are once again
moving forward on faith. We are hopeful that we
can construct the
shell and floor without exceeding our mortgage
limit.
Philip
|
Saturday, February 24, 2007
Today I met the J&J Landscape Design Company Inc. at the church
at 9:00 a.m. Just kidding!!!! I met with Joyce
and Jennifer, two
Purdue seniors who are doing the landscape
design for Baker Chapel.
It is their senior project. I can tell you that
I am more impressed
by this two fine ladies, more than the first
time I met with them.
They really care about this project. They had
several sketches and
ideas, and many possibilities. About 12 people
came to here their
ideas as well. We made a few suggestions. They
left their sketches
for me to share with the congregation tomorrow.
I also learned today
that yesterday was Scott's birthday. He said,
the honor of placing
the cross on top of the steeple was the best
birthday present ever.
Five volunteers worked today. Greg G. installed
all the steel door
frames that had been painted. The rest of us
worked on many different
areas. We traced some wires, to identify a
missing electrical
connection. Sid and Jerol made the connection of
the ground wire from
the cross. I patched some holes in the drywall
(firewall) above the
drop ceiling. The building inspector noted we
had to have these areas
completely sealed. We installed several ceiling
tiles. All of the
ceiling tiles are in the infant room, adjacent
restroom, youth room,
fellowship hall, and over half of the big
hallway are complete. Greg
P. was the other volunteer today. He installed
several of the above
mentioned tiles. I went to town today for lunch,
and attended another
church this evening as a fundraiser for a needy
family. At both
places many people saw the steeple go up on the
evening news last
night. It is the "talk of the town" how nice it
looks.
Philip
|
Friday, February 23, 2007
Volunteers installed a couple door frames and worked on
electric. The steeple arrived at about 9:30 a.m.
The crane arrived
at 10:00 a.m. At 11:00 a service for "The
Consecration of The
Steeple" led by Rev. Randy Anderson, was held in
the sanctuary. Over
75 people attended this service. The cross that
goes on top of the
steeple was brought into the sanctuary for this
service. Those
attending the service could write their name
(with a marker) on the 4
ft. long tubing that connected the cross with
the steeple. The
steeple was transported on a trailer laying
down. The top of the
steeple pointed forward on the trailer. The
crane was secured to the
top of the steeple. The steeple was on a large
hinge pin and as the
crane lifted up the trailer slowly moved
forward. This caused the
steeple to stand upright. The hinge pin was
removed and the steeple
hung freely from the crane. The bottom skirt was
bolted to the
steeple. Before the steeple was lifted, Bonnie
Watson had requested
that we write a scripture inside the steeple. I
wrote John 3:16 "For
God so loved the world that he gave his one and
only Son, that whoever
believes in him shall not perish but have
eternal life." The steeple
was placed on the base at 1:10 p.m. The holes
were marked for the
bolts. The steeple was removed to drill the
holes for the bolts. The
steeple is secured with eight 5/8 long threaded
rods. The steeple was
placed back on the base and bolted. Once the
bolts were tightened,
the crane was unhooked. The crane was then
hooked to a basket. Scott
Brewster was selected to go up in the basket to
attach the cross.
Scott first placed the connecting tubing into
the steeple. At 2:50
p.m. the cross was set into place. When this
took place the remaining
people in attendance clapped, and those watching
from their vehicles
honked their horns. It is hard to describe in
words the inner feeling
of seeing this take place. This steeple is
beautiful. The base of
the steeple is 7 feet 8 inch square. The skirt
that was added to the
bottom is 13 feet wide.The steeple base is 38
feet from the ground.
The steeple is 29 feet 4 1/2 inches tall. The
cross is 5 feet tall,
with the cross member being 2 feet 2 inches
wide. Their is a 12 inch
lightning protection rod on top of the cross.
You can do the math and
see that the tip of the rod is over 73 feet from
the ground. Pictures
will be available on the website soon.
Philip
|
Thursday, February 22, 2007
Kevin, Greg G. and Greg P. finished preparing the steeple base.
Mike installed more ceiling tiles around the
borders. Carl painted
more door frames. Volunteers worked on
electrical connections and
clean-up.
Philip
|
Wednesday, February 21, 2007
Kevin and Greg Green started the final preparations to the
steeple base. The steeple is scheduled to be
delivered and installed
Friday of this week. They also installed trim
work around the attic
access doors, and started to shim the windows.
Sid and Jerry made the
final connections to some of the lights in the
sanctuary. Mike has
finished most of the ceiling frames. He will
install ceiling tiles
around the border of every room. After
inspection, volunteers will
install the remaining tiles.
Philip
|
Tuesday, February 20, 2007
Mike installed the ceiling frames in the men's restroom and
finished the sound room frames. Volunteers wired
the lights in the
library, nursery, infant room and restroom next
to the nursery. Carl
took some of the steel door frames home to spray
paint.
Philip
|
Monday, February 19, 2007
Brock finished spraying the walls in the sanctuary last night.
Mike installed the ceiling frames in the women's
restroom, and started
on the sound room today. Volunteers wired the
lights in the youth
room, and storage room. Kevin painted the inside
of the bulk head in
the sanctuary this evening. The library still
needs a coat of paint,
and several areas need touch-up work, and the
painting will be
complete.
Philip
|
Friday, February 16, 2007
Mike from Midwest installed the ceiling frames in the nursery,
infant room and the restroom next to the nursery
today. Volunteers
worked on securing lights with wires attached to
the ceiling. This is
a code requirement in case of an earthquake. The
steel door frames
for the inside doors were delivered today.
Franks Heating worked on
connecting duct-work to the vents and registers.
I stopped by the
church tonight at 9:30 p.m. and Brock Holder was
applying the finish
coat of paint to the sanctuary walls.
Philip
|
Thursday, February 15, 2007
Volunteers wired the lights in the fellowship hall today. They
also installed some switches and receptacles.
Philip
|
Wednesday February 14, 2007
HAPPY VALENTINE'S DAY
Workers finished installing the ceiling frames in the fellowship
hall. They also did the ceiling frame in the
youth room and the
office. Volunteers wired the lights in the
hallway.
Philip
|
Tuesday, February 13, 2007
Mike and Ben started installing the drop ceiling frames in the
fellowship hall today. They also did the frames
in the
mechanical/closet next to the youth room. Three
workers from Frank's
Heating started installing the vents and
connecting to the duct-work,
in the ceiling grids in the areas that are
completed. Jerry and Sid
wired the light in the pantry, several
receptacles, and started on the
lights in the hallway. It rained most of the
day, turning to freezing
rain, then snow after dark.
Philip
|
Monday, February 12, 2007
Mike and Ben from Midwest worked on the ceiling frames today.
They finished the hallway, did the pantry next
to the kitchen and the
closet in the fellowship hall. Volunteers wired
the lights in the
classroom and minister's office. Today is
Logan's 18th birthday!!!!
Philip
|
Saturday, February 10, 2007
Six volunteer's worked today. We scraped drywall mud from the
floors, swept, cleaned, and vacuumed. We moved
everything out of the
fellowship hall, and put some of the things that
are not needed, in
the storage trailer.
Philip
|
Friday, February 9, 2007
Mike with Midwest worked today. He started installing the drop
ceiling frames in the big hallway. Volunteers
worked on installing
the lights in one of the classrooms, and the
minister's office. Brock
Holder and his helper John came this evening
under the cover of
darkness. They are scheduled to work Sat. at
their "real paying
jobs". So they worked at the church tonight.
They painted the closet
in the fellowship hall, coat closet, sanctuary
ceiling and the
sanctuary walls. They painted several gallons of
paint. These guys
are a real blessing to Baker Chapel.
Philip
|
Thursday, February 8, 2007
Three drywall finishers worked today. They textured the walls in
the sanctuary and finished the sound room.
Except for a few small
areas in a couple closets, most of the drywall
mud-work is complete.
They also installed the drop ceiling frames in
one classroom and the
minister's office. Volunteers installed lights
in the kitchen,
classroom, office, and more receptacles. The
kitchen lights are
connected and hooked to the permanent light
switch. Volunteers
continue to clean-up on a daily basis.
Philip
|
Wednesday, February 7, 2007
Two drywall finishers worked today. They textured the ceiling in
the sanctuary. These guys are workers from
Midwest Construction.
They will also install the frames for the drop
ceilings. They
installed the drop ceiling frames in the
kitchen. Several boxes of
ceiling tiles were delivered today. Electrical
volunteers started
installing receptacles in areas that the
painting is complete.
Philip
|
Monday, February 5, 2007
Six volunteers from Tri-State Painting painted today. Other
Baker Chapel volunteers helped paint and
clean-up. One drywall
finisher worked today. The interior design
committee met with the
carpet guy this evening. They finalized what
colors go where, and
took measurements.
Philip
|
Saturday, February 3, 2007
TODAY WAS PAINT DAY!!!!!!!!!!!!!!
Today, volunteers began painting at Baker Chapel. Cletus Miller,
Gene Feagley and Brock Holder are three angels
from God. These guys
are professional painters. They have volunteered
their time and
equipment. They are using airless electric
sprayers. The three of
them along with nine other volunteers, all Baker
Chapel members began
painting at 8:00 a.m. today. They applied two
coats of paint in the
ministers office, work office, 2- classrooms,
mechanics room,
kitchen , narthex, and fellowship hall. They
also applied one coat in
the foyer and the men's restroom. They sprayed
and rolled on over 100
gallons of paint today. I was unable to help
today. Logan and I
attended the Purdue Ag Alumni Fish Fry in
Indianapolis today. We had
the privilege to here The story of Apollo 13.
The guest speakers were
Captain James Lovell, Apollo Astronaut Commander
and Gene Kranz,
former NASA Director of Mission Operations. In
Captain Lovell's
speech, he stated that their are three kinds of
people in the world.
First, "Those people who make things happen".
Second, "Those people
who watch things happen". And third, "Those
people 'who ask' What
happened"? Today, the people who volunteered,
are people who "Make
things happened". We continue to be blessed.
Philip
|
Friday, February 2, 2007
Two drywall finishers worked today. They sprayed the splatter
finish on the walls and ceiling in the front
entrance. Volunteers
worked at moving items around and covering them
with plastic, for
protection while painting. They also did
clean-up work. We are
hoping some volunteers come to help paint
tomorrow.
Philip
|
Thursday, February 1, 2007
One drywall finisher worked today. He started applying the
texture on the ceiling in the sanctuary. He
completed the bulkhead
around the outside edge of the sanctuary.
Several gallons of paint
and supplies were delivered today. Their are
seven different colors
including the primer.
Philip
|
Wednesday, January 31, 2007
One drywall finisher worked today. Volunteers covered some of
the electrical boxes with paper and tape. This
is being done to
protect them, when we start painting. The paint
with be sprayed on.
We will paint one coat of primer, and two coats
of paint. Last Sunday
the congregation voted on their choice of color
schemes. We have
chosen the colors of paint and carpet for the
hallway, fellowship hall
and the sanctuary, and the tile for the
entrance. The decorating
committee will choose the remaining paint
colors.
Philip
|
Tuesday January 30, 2007
Two drywall finishers worked today. Volunteers finished covering
the windows and doors with plastic. They
delivered some of the frames
and supports for the drop ceilings today.
Volunteers continue to
sweep and vacuum up the drywall dust.
Philip
|
Monday, January 29, 2007
One drywall finisher worked today. Volunteers worked on covering
the windows and window frames with plastic. This
was in preparation
for painting. Which we hope to be able to start
on next week.
Philip
|
Saturday, January 27,2007
Today I met two fantastic people. Joyce and Jennifer are both
seniors at Purdue University. They will graduate
in May with a degree
in Landscape & Horticultural Design. They have
been chosen by God,
and then chosen by their Professor to design the
landscaping at Baker
Chapel. Several weeks ago I was contacted by two
different people
about a program, that Purdue Professor Dr.
Michael N. Dana was looking
for community landscape planting projects. I
submitted Baker Chapel
as a possible project, and we have been
selected. I had the joy and
pleasure to meet Joyce and Jennifer in person
today. They are two
very fine young ladies who are eager to help
with our project. We
were scheduled to meet at the church at 8:00
a.m. this morning. When
I arrived at 7:50 a.m. they were already taking
pictures. I spent
time with them walking the grounds, going over
blue prints of our
construction, and sharing ideas from members of
their suggestions.
Greg also came this morning and spent time
answering their questions
and giving them a tour of the building. I left
for a while to attend
another meeting. Logan helped them take soil
samples and assisted
them until I returned. Gary Michel, our County
Extension Educator
came today to meet them as well. We went and did
an inventory and
identified the trees that has been donated to us
in Sept. from
the "New York Says Thank You Foundation". This
trees have been
winterized and protected until we were prepared
to plant them. Joyce
and Jennifer had many questions. They truly seem
excited and eager to
help with the project. We all went to lunch in
town. Gary jumped at
the chance for me to buy him and the others
lunch. I felt that was
the least I could do. Gary was one of the people
who contacted me
about this program. The other person who
contacted me was Larry
Ordner. Larry is the Regional Director for our
U.S. Senator Richard
Lugar. A special thanks to both of you for
sending me the
information. After lunch, we returned to the
church to discuss the
possible time-line for their work. And the
process that they will be
following. The Boonville FFA chapter, as well as
the local Master
Garden club has volunteered to help with the
planting of the
landscaping. This evening Greg met with the
person who is going to
paint the church, and to develop a schedule.
Philip
|
Friday, January 26, 2007
Two drywall finishers worked today. They continue to work in the
sanctuary. While the joint compound dries in the
sanctuary, they
apply the final coat and do sanding in other
areas. Jerry Lutz has
hand crafted a cover plate for each of the
receptacles, for the window
candles. They are made of popular wood to match
the window frames. I
have not seen them yet, but I have been told
they are beautiful, and
look perfect. I am sure it took him many hours.
Thank you Jerry.
Others continue to wipe dust from the walls, and
vacuum the floors.
Philip
|
Thursday, January 25, 2007
One drywall finisher worked today. Volunteers installed two
pull-down access stairs. One in the storage
above the classroom, and
one in the utility closet.
Philip
|
Wednesday, January 24, 2007
Two drywall finishers worked today. They have been applying
compound in the sanctuary, and the final coats | | |